SSR MINING ANNOUNCES 20-YEAR LIFE OF MINE PLAN FOR MARIGOLD BASED ON EXPANDED 4.6 MILLION OUNCE MINERAL RESERVE • NPV 5% OF $3.3 BILLION AND $3.8 BILLION AT CONSENSUS AND SPOT PRICES, RESPECTIVELY • MARIGOLD AVERAGES ANNUAL PRODUCTION OF 231,000…
SSR MINING ANNOUNCES 20-YEAR LIFE OF MINE PLAN FOR MARIGOLD
BASED ON EXPANDED 4.6 MILLION OUNCE MINERAL RESERVE
• NPV
5%
OF $3.3 BILLION AND $3.8 BILLION AT CONSENSUS AND SPOT PRICES, RESPECTIVELY
• MARIGOLD AVERAGES ANNUAL PRODUCTION OF 231,000 OUNCES OF GOLD FROM 2027 TO 2031
• LIFE OF MINE GOLD PRODUCTION TOTALS 3.3 MILLION OUNCES AT AN AVERAGE ALL-IN SUSTAINING COST (“AISC”) OF $2,062 PER
OUNCE SOLD
(1, 2)
• SSR MINING’S U.S. PORTFOLIO NOW ANCHORED BY TWO MULTI-DECADE ASSETS IN MARIGOLD AND CC&V HOSTING TOTAL
COMBINED GOLD MINERAL RESERVES OF 7.3 MILLION OUNCES, WITH AN ADDITIONAL 6.5 MILLION OUNCES OF M&I RESOURCES
AND 2.3 MILLION OUNCES INFERRED
DENVER – SSR Mining Inc. (Nasdaq/TSX: SSRM) (“SSR Mining”, the “Company”, “we”, “us”, or “our”) announces the
results of a Technical Report Summary (“TRS”) for the Marigold Gold Complex (“Marigold”) in Nevada, USA (the “2026
Marigold TRS”).
Highlights of the 2026 Marigold TRS:
( 1,2)
• After-tax NPV
5%
of $3.3 billion at consensus gold prices averaging $3,948 per ounce over the 20-year life of mine
• Average annual gold production of 231,000 ounces over the five-year period from 2027 to 2031, 201,000 ounces
through 2040, and 169,000 ounces over the life of mine
o Over the period of active mining, annual after-tax operating cash flow and after-tax free cash flow averages $354
million and $273 million, respectively, based on consensus gold prices
• Gold Mineral Reserves at Marigold total 4.6 million ounces, an increase of 43% from the 3.2 million ounces at year-end
2025, with a significant Mineral Resource base demonstrating additional potential for longer-term upside
o Measured & Indicated Mineral Resources, exclusive of Mineral Reserves, total 1.7 million ounces of gold as
compared to the 1.8 million ounces of M&I Resources as of year-end 2025
o Inferred Mineral Resources are an additional 0.3 million ounces of gold as compared to the 0.5 million ounces as
of year-end 2025
• Inclusive of mined depletion, gold Mineral Reserves in the 2026 Marigold TRS increased significantly as
compared to the 2024 TRS, while Indicated and Inferred Mineral Resources remained materially unchanged
over the same time period
o The gold prices used in the calculation of Marigold Mineral Reserves and Mineral Resources are $2,200/oz and
$2,500/oz, respectively
• 2026 Marigold TRS incorporates the maiden life of mine plan for the Buffalo Valley project (“Buffalo Valley”) with 0.7
million ounces of gold Mineral Reserves and first production expected in 2029
o Growth capital investment over the life of mine totals $542 million, including the development of Buffalo Valley and
its stand-alone heap leach facility, as well as fleet additions to support a 33% increase in overall mining rates at
Marigold to an average of 138 million tonnes per annum
o Investment in fleet modernization and expansion will improve productivity and operational flexibility to support the
multi-decade mine life at Marigold
(1 )
The Company reports non-GAAP financial measures including after-tax free cash flow to manage and evaluate its operating performance at its mines. See “Non-
GAAP Financial Measures” at the end of this press release for an explanation of these financial measures and a reconciliation of these financial measures to
operating cash flow, which is the most comparable GAAP financial measure.
(2)
The calculations of average annual gold production use 2027 as Year 1, since 2026 represents a partial year of operation in the TRS. From 2027 onwards, life of
mine gold production at Marigold is 3.2 million ounces at an AISC of $2,005 per ounce sold.
SSR MINING | PAGE 2
Rod Antal, Executive Chairman of SSR Mining, said, “Today’s updated life of mine plan reinforces Marigold’s position as a
premier, multi-decade asset in the United States. Over the next three years, we plan to invest in Marigold to modernize the
operation for future success through fleet and heap leach pad expansions that aim to improve its operational flexibility and
reliability.
Importantly, over the next five years we expect Marigold will average more than 230,000 ounces of gold production annually,
aligned with the prior TRS expectations and supporting average annual gold production of approximately 360,000 ounces
from our U.S. assets over that period. Longer-term, the mine is expected to average 200,000 ounces of gold production
annually through 2040, delivering a more than 50% increase in life of mine production over the prior mine plan.
Investing in organic growth is one of the key pillars of our capital allocation strategy, and this TRS provides a clear pathway
for us to execute on that strategy and create value for shareholders. This new mine plan increases Mineral Reserves by
43% as compared to year-end 2025 while Indicated and Inferred Resources remain essentially unchanged, demonstrating
our track record of exploration and resource development success while highlighting further potential for additional mine life
extension in the future.”
The TRS, with an effective date of May 1, 2026, has been prepared in accordance with S-K 1300 and will be available on
October 13, 2026 on the Company’s website and on a Current Report on Form 8-K to be filed with the U.S. Securities and
Exchange Commission (“SEC”).
SSR MINING | PAGE 3
Figure 1: 2026 Marigold TRS – Production Summary (in koz)
Table 1: 2026 Marigold TRS – Key Metrics
(3)
Five-Year Profile Active Mining Total Mine Life
Unit 2027 – 2031 2027 – 2040 2027 – 2050
Total Gold Production Au koz 1,153 2,816 3,208
Average Annual Gold Production Au koz 231 201 169
Total Operating Cash Flow (GAAP) $M $2,353 $4,955 $5,978
Total Capital Costs (GAAP)
(4)
$M $817 $1,133 $1,231
Total Free Cash Flow (non-GAAP)
(5)
$M $1,536 $3,822 $4,747
Average Annual Free Cash Flow $M $307 $273 $253
Cost of Sales (GAAP) $/oz sold $1,990 $1,959 $1,793
Cash Costs (non-GAAP)
(5)
$/oz sold $1,991 $1,960 $1,795
All-In Sustaining Costs (non-GAAP)
(5)
$/oz sold $2,279 $2,183 $2,005
(3)
Five-Year Profile metrics are from 2027 to 2031, Active Mining metrics are from 2027 to 2040 and Total Mine Life metrics are summed over the period of 2027 to
- Average Total Mine Life metrics are calculated over the period 2027 to 2045, as residual heap leaching concludes in 2045.
(4)
Total capital costs include sustaining capital, development capital, and reclamation.
(5)
The Company reports non-GAAP financial measures including after-tax free cash flow and All-In Sustaining Cost (“AISC”) per ounce sold to manage and evaluate
its operating performance at its mines. All cash flow figures are presented after tax. See “Non-GAAP Financial Measures” at the end of this press release for an
explanation of these financial measures and a reconciliation of these financial measures to operating cash flow and cost of sales, which are the most comparable
GAAP financial measures. Cost of sales excludes depreciation, depletion, and amortization.
Table 2: 2026 Marigold TRS – After-Tax NPV Sensitivity
LOM Average
Gold Price
$/oz $3,158 $3,553 Base Case
(6)
$4,342 $4,737
Sensitivity % -20% -1 0% — +10% +20%
NPV5% $M $1,609 $2,471 $3,334 $4,196 $5,058
(6)
Base Case gold price assumption averages $3,948/oz over the life of mine, including the long-term gold price of $3,710/oz starting in 2031. See “assumptions” at
the end of this press release for a summary of gold prices used in the 2026 Marigold TRS.
SSR MINING | PAGE 4
Marigold Mineral Reserves and Mineral Resources (“MRMR”)
(7)
Marigold is located in southeastern Humboldt County, Nevada, United States on the Battle Mountain-Eureka trend,
approximately 5 kilometers south-southwest of the town of Valmy, Nevada. The Marigold Complex includes the Marigold
Mine and the Buffalo Valley and Trenton Canyon deposits. Buffalo Valley is located approximately 24 kilo meters southwest
of the main infrastructure at Marigold. Since commencing operations in 1989, Marigold has produced over 5 million ounces
of gold.
Table 3: 2026 Marigold TRS – MRMR as of May 1, 2026
(100% attributable) Tonnes (Mt) Grade (g/t) Gold (Moz)
Total P+P Reserves 359 0.40 4.63
M&I Mineral Resources 131 0.40 1.66
Inferred Mineral Resources 29 0.31 0.29
Combining Marigold with the Company’s CC&V gold mine in Colorado established SSR Mining as the third largest gold
producer in the USA. Both operations now feature multi-decade mine lives and host significant Mineral Resource bases to
support potential for future growth and extension.
Figure 2: SSR Mining – MRMR by U.S. Asset
Marigold CC&V USA Consolidated
(7)
Please see “Supplemental Mineral Reserve and Mineral Resource Information” at the end of this press release for additional details. Mineral Resources are
exclusive of Mineral Reserves. Numbers may not add due to rounding.
Figure 3: SSR Mining – Combined U.S. Production Profile
0
50
100
150
200
250
300
350
400
450
500
2027E2028E2029E2030E2031E2032E2033E2034E2035E2036E2037E2038E2039E2040E2041E2042E
Gold Production (koz)
Marigold Gold Production (2026 TRS)CC&V Gold Production (2025 TRS)
SSR MINING | PAGE 5
2026 Marigold TRS Overview
Geological understanding of the Marigold Complex is supported by more than three decades of mining operations, extensive
exploration programs, geologic mapping, geophysical surveys, metallurgical testing, production history, and ongoing
resource definition drilling.
Mining & Processing
The 2026 Marigold life of mine plan features 15 years of active mining and 20 years of total production, inclusive of heap
leach pad rinsing and drawdown. The Marigold Complex mine plan outlined in the 2026 Marigold TRS has five distinct areas
of mining: the main Mackay pit (including the Red Dot and DG80 areas), the North Mackay pits, the Valmy pits, the New
Millennium area, and Buffalo Valley. A separate mining fleet of 8 to 10 trucks and two hydraulic shovels was initially
considered for Buffalo Valley, however, procuring additional trucks and loading units in 2027 allows for accelerated waste
stripping at Marigold ahead of initial development at Buffalo Valley. Peak fleet size in the 2026 Marigold TRS is 45 haul
trucks, six shovels and two loaders. This expanded fleet is then adequate to operate both Marigold and Buffalo Valley
simultaneously over the life of mine and enables increased flexibility in mine planning going forward.
On average, the operating period from 2026 to 2040 includes average mining rates of approximately 380,000 tonnes per
day (138.3 million tonnes per annum) with a life of mine strip ratio of 5.3:1. Stacking rates are expected to average
approximately 20 million tonnes per annum at Marigold over the life of mine, while the Buffalo Valley heap leach facility is
designed to accommodate stacking rates of up to 14 million tonnes per annum. The life of mine gold recovery across
Marigold and Buffalo Valley is 72% over an average of 90 to 120 day leach cycle, with an average stacked grade of 0.44
grams per tonne. Life of mine gold production totals 3.34 million ounces, including approximately 0.3 million ounces of
current work-in-progress inventory recovered over the life of mine.
The Buffalo Valley heap leach facility will be constructed and operated in a manner very similar to the main Marigold facility.
Run of mine ore will be truck stacked in 7.5 meter to 12.5 meter lifts. Following heap leaching, pregnant solution will be
pumped into three Carbon-in Column (CIC) trains for adsorption. Loaded carbon from the adsorption circuit will be
transported to the Marigold elution facility for final recovery, with barren carbon then transported back to the Buffalo Valley
facility. Buffalo Valley will require upgrades to the road connecting to main Marigold facilities, and will require the construction
of approximately 14.5 kilometers of power line from the existing North Peak power line to service the project site.
Table 4: 2026 Marigold TRS – Operating Metrics Summary
Unit Life of Mine
Total Material Mined Mt 1,881
Average Daily Mining Rate ktpd 380
Total Ore Mined Mt 298
Total Waste Mined Mt 1,583
Strip Ratio
W:O 5.3:1
Total Ore Processed Mt 298
Average Daily Processing Rate ktpd 58
Ore Grade Stacked g/t 0.44
Contained Gold Stacked koz 4,255
Gold Recovery
% 72%
SSR MINING | PAGE 6
Infrastructure
The Marigold Complex is accessed via a five kilometer public road connected to the U.S. Interstate Highway 80. Marigold
is grid connected, while water for operations is supplied by three existing groundwater production wells. Mine dewatering
wells are used to supplement production wells when needed. Where possible, operations at Buffalo Valley will leverage
existing infrastructure at Marigold, including the maintenance facilities and administrative offices. A tailings storage facility
(TSF) is present at Marigold but has been decommissioned since operations transitioned solely to heap leaching.
Operating Costs
Forecasted operating cost estimates related to the development of the 2026 Marigold TRS are derived from annual budgets
and historical actuals over the long life of the current operation. The life of mine operating cost estimate for the Marigold
Complex is $16.78 per tonne of stacked ore. Life of mine operating costs in the 2026 Marigold TRS do not account for non-
cash inventory movements and other minor non-cash items that impact the Company’s calculation of cash costs and AISC.
Table 5: 2026 Marigold TRS – Mine Operating Cost Summary
Operating Costs Life of Mine ($M) Stacked ($/Tonne)
Mining & Maintenance $3,741
$12.57 ($1.99/t moved)
Processing $804
$2.70
G&A $451
$1.51
Total Costs $4,996
$16.78
Labor and diesel are the two largest components of operating costs at Marigold. Diesel prices for the economic analysis
were based on the latest available consensus forward-looking price forecasts and compared to those used in other
published studies. Near-term diesel price assumptions in the 2026 Marigold TRS average approximately $4.00/gallon before
normalizing to $3.00/gallon over the long-term. The effective NSR royalty on the Marigold property in the 2026 Marigold
TRS is approximately 6.9%, while the effective NSR royalty for the Buffalo Valley deposit is fixed at 3.5% over the life of
mine.
Figure 4: 2026 Marigold TRS – Cost Breakdown
SSR MINING | PAGE 7
Capital Costs
Total life of mine capital outlined in the 2026 Marigold TRS is $1,385 million, including $669 million in sustaining capital.
Sustaining capital costs include:
• Replacement of mining equipment as it reaches its economic life during the active mining period. The majority of