TORONTO, Nov. 18, 2026 (GLOBE NEWSWIRE) -- Allied Gold Corporation (TSX: AAUC; NYSE: AAUC) (“Allied” or the “Company”) is pleased to provide an update on the installation of full power supply infrastructure at the Kurmuk Mine. The Company is also progressing exploration and design activities at Tsenge to support its advancement and development as an additional mining area and source of ore for the mill. The Tsenge Trend is a priority exploration and development area that the Company is advancing to increase production and extend the mine life.
Full Power Supply Infrastructure Advancing to Commercial Production
Following the successful grid connection energization in September, Ethiopian Electric Power, through its contractor, has begun assembling, installing and commissioning the required equipment and materials for the automated grid stabilization system. This represents an important milestone in the final phase of the power infrastructure program, as the completion of the full power system will enable the grid to meet the full load requirements of normal plant operation at the Kurmuk Mine without relying on generators.