ASX Announcement 23 April 2026 Q1 2026 Activities Report For the Quarter ending 31 March 2026 (‘Q1’, ‘March Quarter’ or ‘the Quarter’) Quarterly Highlights • Total Recordable Injury Frequency Rate (TRIFR) of 0.43 with only one recordable injury…
ASX Announcement
23 April 2026
Q1 2026 Activities Report
For the Quarter ending 31 March 2026 (‘Q1’, ‘March Quarter’ or ‘the Quarter’)
Quarterly Highlights
•
Total Recordable Injury Frequency Rate (TRIFR) of 0.43 with only one recordable injury during Q1
•
Group gold production of 59,603 ounces (oz) (Q4 2025: 65,918oz) in line with expectations at both
Mako (Senegal) and Syama (Mali)
•
All-In Sustaining Costs (AISC) of $2,210/oz (Q4 2025: $1,877/oz) in line with guidance as cost
reductions partially offset higher royalty payments due to record average realised gold prices
•
Capital expenditure of $33.4 million (Q4 2025: $28.7 million) consisting of $14.3 million nonsustaining, $6.9 million of sustaining, $5.1 million exploration capital spend, $7.1 million at Doropo and
Mako Life Extension Project (MLEP). Remains on track with guidance ($310 - 360 million)
•
Operating cash flow generation of $119.8 million (Q4 2025: $85.7 million) (operating cash flow before
capital expenditure, exploration and working capital)
•
EBITDA of $202.9 million (Q4 2025: $104.9 million); $337.6 million revenue (Q4 2025: $201.5 million)
•
Net cash of $315.4 million (Q4 2025: $209.0 million), including cash, cash equivalents and bullion of
$327.6 million. Drawn overdraft balances and equipment financing were $12.2 million
•
Proceeds of $31.9 million received from the sale of Resolute's stake in Loncor Gold
•
Key milestones reached at the Doropo Project (Côte d'Ivoire) including receipt of the mining permit
and formal approval of Final Investment Decision (FID)
•
Strategic Memorandum of Understanding (MoU) signed with Nimba Mining Company regarding
the potential co-development of gold projects in Guinea
•
Ore Reserves and Mineral Resource Statement for 31 December 2025 published:
•
Total Mineral Resources increased by 60% to 17.6 Moz Au with the acquisition of the Doropo and
ABC projects and exploration success at Bantaco and La Debo
•
Total Ore Reserves increased by 55% to 6.8 Moz Au with the addition of Ore Reserves at Doropo
and Tomboronkoto offsetting mining depletion in Mako and Syama
• Promising drill results at ABC Project (Côte d'Ivoire) including 73m at 0.8 g/t Au from 2m along strike
of the existing MRE at Kona South
•
Scoping Study for the ABC Project remains on track for completion in Q2 2026
•
On track to meet production guidance of 250 - 275 koz. Group AISC of $2,000 - 2,200/oz is
maintained, however is subject to change at current elevated gold prices and higher fuel costs
ASX Announcement
Note: Unless otherwise stated, all dollar figures are United States dollars ($). AISC guidance is based on $4,000/oz gold price.
Resolute Mining Limited (Resolute, the Company or the Group) (ASX/LSE: RSG), the West Africafocused gold miner, is pleased to present its Quarterly Activities Report for the period ended 31 March
2026.
Chris Eger, Chief Executive Officer, commented,
“It has been a positive start to 2026 at both our operations and at our development and exploration
projects.
Our operations continued to perform in line with expectations and generated $119.8 million of operating
cash flows helping boost our net cash position to $315.4 million. We remain on track with production
guidance which is weighted to H2 as the Syama Sulphide Conversion Project is commissioned and ramps
up.
In Cote d'Ivoire we have had a very successful Quarter at ABC and Doropo. At ABC we have been
focusing on strike extensions of the Kona South and Central deposits that have an existing MRE of 2.2
Moz. With the success we have been seeing at ABC, including an intercept from surface of 73 m grading
0.8 g/t, we will continue drilling in order to further expand resources. During Q1 we started a scoping
study for ABC, based on the existing MRE, which we expect to release in Q2. At Doropo we achieved
two major milestones: receipt of our mining permit and formal approval of FID. In April ground clearance
activities started and we remain on track for first gold in H2 2028.
In Senegal, stockpile processing at Mako continued to perform extremely well. Additionally, strong
progress was made on technical and permitting workstreams for the MLEP. Internal technical studies
currently indicate annual gold production levels of 75 - 85 koz over seven years from the Tomboronkoto
and Bantaco deposits at a capital cost of between $125 - 150 million. We are continuing with optimizations
and are confident of further improvements to the project.
During the Quarter we also signed a strategic MoU with Nimba Mining Company to evaluate projects in
Guinea. This aligns with Resolute's strategy of building a pipeline of high-quality growth opportunities in
established West African gold jurisdictions and complements our other activities in Guinea.
While the ongoing situation in the Middle East has not resulted in any direct disruptions to our supply
chain, we are closely monitoring developments. There is a potential for increased AISC due to rising fuel
prices, which could impact our operational costs in the coming quarters. At this stage, we are proactively
managing these risks and, where possible, minimizing any impacts.
Overall, I am pleased with the Group's activities and financials in Q1. We remain confident in delivering
against our guidance, supported by a robust balance sheet and experienced teams, that are well placed
to continue performing across the business as we move into Q2.”
ASX Announcement
Webcast and Conference Call
Resolute will host a conference call for investors, analysts, and media on 23 April 2026, to discuss the
Company’s Quarterly Activities Report for the period ending 31 March 2026. This call will conclude with
a question-and-answer session.
Conference Call: 6:00pm (AEST, Sydney) / 9:00am (BST, London)
Webcast registration link: https://sparklive.lseg.com/ResoluteMiningLtdAustralia/events/c3dd5dd830b9-42d2-ae18-47b19e044b88/resolute-mining-ltd-q1-2026-conference-call
Written questions can be submitted using the ‘Ask a Question’ button on the webcast page. Those
wishing to ask questions as part of the Q&A should use the conference call facility (please join five
minutes before the start time).
Conference call registration link: https://registrations.events/direct/LON34665289
A presentation, to accompany the call, will be available for download on the Company’s website:
https://www.rml.com.au/investors/presentations/.
ASX Announcement
Group Operations Overview
Units
March
2026
Quarter
December
2025
Quarter
% Change
March
2025
Quarter
Ore Mined
t
794,436
858,470
(7)%
1,345,796
Mined Grade
g/t
2.21
2.14
3%
1.97
Ore Processed
t
1,633,013
1,581,115
3%
1,550,187
Processed Grade
g/t
1.40
1.51
(7)%
1.79
Group Summary
Mining
Processing
Recovery
%
81
84
(4)%
84
Gold Poured
oz
59,603
65,918
(10)%
75,497
oz
$/oz
69,352
4,858
49,941
4,023
39%
21%
64,322
2,840
Total Capital Expenditure
$m
33.4
28.7
16%
29.4
Net Cash
AISC
$m
$/oz
315
2,210
209
1,877
51%
18%
100
1,708
Sales
Gold Sold
Average Realised Price
Financials
Table 1: Resolute Group Operational Performance Summary
During the Quarter, Resolute processed over 1.63 Mt across Syama (Mali) and Mako (Senegal) at an
average milled head grade of 1.40 g/t. In Q1 the Group produced 59,603 oz of gold at an AISC of
$2,210/oz.
ASX Announcement
Environmental and Social Update
Resolute’s year-to-date (and quarterly) TRIFR as of 31 March 2026 improved to 0.43 (full-year 2025:
1.87) with one recordable injury during the Quarter. This is a significant decrease on previous quarters
with improvements to preventive safety measures and leading indicators during H2 2025.
In Q1, Resolute recorded no significant environmental incidents, regulatory non-compliances, and no
reportable community grievances.
During the Quarter, Resolute published its 2025 Sustainability Report, Climate Report and Greenhouse
Gas Emissions Calculation Method Statement. These climate-related disclosures were prepared in
accordance with the Australian Sustainability Reporting Standards (ASRS).
Resolute is undergoing external assurance against the Responsible Gold Mining Principles and Conflict
Free Gold Standard with assurance reports expected in Q2. In addition, Resolute will be audited against
the Responsible Gold Guidance in Q2. ISO14001 Environmental Management and 45001 OHS
Management audits at Syama are now expected in Q4.
In Senegal, the focus has been on the Mako Life Extension Project, comprising technical studies in
support of the Tomborokoto and Bantaco satellite deposits, and expansion of the existing Mako Mine
process plant. For the Tomboronkoto Satellite Deposit, the Environmental & Social Impact Assessment
(ESIA) report was validated by the environmental regulator in advance of ministerial approval.
Consultation is ongoing with potentially affected persons for the resettlement of Tomboronkoto village,
who have selected their preferred site for detailed resettlement planning. In parallel, formal ESIA studies
are ongoing for (i) the expansion of the Mako Mine process plant, including a new Tailings Storage Facility,
and (ii) the Bantaco Satellite Deposit. Draft ESIA reports for these two project components are scheduled
for submission to the environmental regulator in Q2.
At the Doropo Project, Côte d’Ivoire, the first phase of land acquisition is nearing completion in preparation
for the commencement of early works construction activities in Q2 2026. Strategies have also been
developed in consultation with project affected communities to enhance local economic participation
through project-related employment and procurement opportunities.
At Syama, Mali, a detailed feasibility study and accompanying ESIA were initiated for the development of
a third Tailings Storage Facility. This follows satisfactory results from the completion of multi-criteria
alternatives analysis for tailings management and conceptual design studies on the preferred design
option.
ASX/LSE: RSG I rml.com.au
Page 1 of
ASX Announcement
Mali
Syama Operations
Syama gold production for the Quarter was 43,802oz at an AISC of $2,227/oz. The operational
performance is set out in the table below.
Summary
Units
March
2026
Quarter
December
2025
Quarter
% Change
March
2025
Quarter
Mining
Sulphide
Ore Mined
t
711,718
711,984
—%
512,485
Mined Grade
g/t
2.23
2.20
1%
2.45
Ore Mined
t
82,718
146,486
(86)%
221,846
Mined Grade
g/t
2.06
1.83
20 %
1.41
Ore Processed
t
627,706
582,931
8%
587,009
Processed Grade
g/t
2.36
2.34
1%
2.35
Oxide
Cost
Processing
Sulphide
Recovery
%
76
78
(2)%
77
Gold Poured
oz
36,682
35,998
2%
36,143
Gold Sold
oz
47,070
18,861
150 %
30,733
Ore Processed
t
431,768
394,486
9%
429,183
Processed Grade
g/t
0.64
1.02
(37)%
1.03
Recovery
%
76
81
(6)%
84
Gold Poured
oz
7,120
11,165
(36)%
12,091
Gold Sold
oz
7,120
11,165
(36)%
12,091
Syama combined
Capital Expenditure
$m
20.6
18.1
14 %
23.8
AISC
$/oz
2,227
1,779
25 %
1,835
Oxide
Table 2: Syama Production and Cost Summary
At Syama, production delivered a strong start to the year, with 43,802 oz of gold poured in Q1 across
both sulphide and oxide operations, in line with the Company’s plan. Operational performance remained
robust, with both processing plants achieving consistently high utilisation and availability, supporting total
ore throughput of approximately 1.06 Mt for period.
As expected, oxide mining was lower than the prior Quarter with material primarily sourced from the A21
(Syama North) open pit. Oxide mining is expected to continue in Q2 to build stockpiles for processing
later in the year. In Q1, the primary source of oxide feed was previously stockpiled material, delivering a
ASX/LSE: RSG I rml.com.au
5
ASX Announcement
consistent and reliable average head grade of 0.64 g/t, demonstrating the strength and flexibility of the
operation's stockpile management system.
During Q2, Stage 1 of the Syama Sulphide Conversion Project (SSCP) commissioning will move to
processing a blended sulphide feed sourced from A21 fresh rock, underground sulphide ore, and sulphide
stockpiles.
At the sulphide operation, underground ore tonnes were above target with additional low grade draw
points accelerated, resulting in slightly lower mined grade of 2.23 g/t from the sub-level cave. These low
grade ore tonnes have been stockpiled for SSCP commissioning in Q2.
The sulphide head grade averaged 2.36 g/t as higher grade run of mine ore was processed through
Process Plant 1 (PP1 – historically the sulphide plant). Feed grades are expected to increase slightly to
between 2.4 – 2.5 g/t from the underground production in Q2.
In Q2 sulphide processing activities will undergo a transition with a focus on commissioning of the flotation
plant on Process Plant 2 (PP2 – historically the oxide plant which has been converted to dual purpose
through the SSCP). As expected, sulphide production in Q2 is expected to be lower than Q1 due to a
planned plant shutdown to tie in the SSCP and upgrade the roaster. As per Figure 1, Syama remains on
track for full-year production guidance of 195 - 210 koz with production weighted to the second half of the
year.
Figure 1: 2026 Syama actual gold production (koz) and guidance
During Q1 capital expenditure was $20.6 million split $6.3 million and $14.3 million between sustaining
and non-sustaining capital respectively. Expenditure for the Quarter includes Underground production
ASX/LSE: RSG I rml.com.au
6
ASX Announcement
mobile machinery, and Tailings Storage Facility lift, with $8.0 million spent on the SSCP and Roaster
upgrade as well as $5.7 million of sustaining waste capital. Syama remains on track for its capital
expenditure guidance of $110 - 125 million.
Disruption in the Middle East has affected global logistics, supply chains and cost of materials. In
response, Resolute has increased procurement activity and on-site inventory levels for selected critical
consumables as a risk mitigation measure, with the objective of supporting continuity of operations. At
this stage, the business has not been materially impacted by consumable shortages, and supply
disruptions have been successfully managed. However, the company is experiencing elevated costs for
some inputs, including fuel and key reagents, which may impact overall operating costs if these price
trends persist. Management continues to closely monitor market conditions and maintain contingency
plans to minimize potential adverse effects on production and costs.
At Syama, storage capacity has been increased for both light fuel oil (LFO), used for mobile equipment,
and heavy fuel oil (HFO), used for power generation. LFO storage on site is currently approximately 77%
of total capacity equating to over 50 days of operational coverage at current consumption rates. HFO
storage capacity approximately 90%, providing over 40 days of power generation coverage. For both
LFO and HFO, deliveries have continued largely as scheduled, however unit costs have increased. Fuel
prices in Mali are regulated by the government and in April LFO prices increased by approximately 50%.
If the current prices for fuel are maintained for the remainder of the year, we expect an increase to AISC
of approximately $75/oz for the full-year.
Key processing reagents, including cyanide, PAX and Sasol products, currently exceed three months of
on-site inventory. Other consumables remain in transit, with some experiencing minor delays, although
no material operational impacts have been reported to date.
Explosive inventories at Syama continue to fluctuate in line with supply conditions. Current on-site
inventories provide more than one month of operational coverage. The Company has continued progress
toward securing a modular emulsion manufacturing facility at Syama. Engagement with Malian authorities
regarding permitting is ongoing, and subject to regulatory approvals, construction and commissioning are
expected to occur in H2.
In Q1 the AISC was slightly above guidance $2,227/oz due to higher royalty payments. Royalty payments
were driven by an average realised gold price during the quarter. The impact of high gold prices on AISC
was approximately $135/oz above the level expected for guidance. Syama remains on track for full-year
AISC guidance of $1,950 - 2,150/oz (at a gold price assumption of $4,000/oz) subject to ongoing fuel
cost pressures.
ASX/LSE: RSG I rml.com.au
7
ASX Announcement
Syama Sulphide Conversion Project (SSCP)
The project remains on track and on budget with no lost time injuries (LTIs) after approximately 1.06
million person-hours worked until the end of March 2026.
During the March 2026 quarter, construction of the flotation circuit was successfully completed, marking
a major milestone for the SSCP and significantly advancing the project towards completion.
Commissioning has now commenced, with activities progressing through Q2, positioning the operation
for a strong ramp-up phase.
Capital expenditure on the SSCP in Q1 was $8.0 million and in line with the full-year guidance for capital
spend of $40 million.
With flotation plant construction substantially complete, focus in Q1 shifted to advancing other critical
components, particularly the secondary crusher and ball mill circuits. Strong progress was achieved
across these areas during Q1, positioning SSCP well for Stage 2 commissioning in Q3.
Looking ahead to Q2, commissioning activities for the flotation plant are on schedule. In April, sulphide
ore feed is planned to commence with handover to operations anticipated toward the end of the month.
Construction activities in the secondary crusher and ball mill areas are expected to continue throughout
Q2.
ASX/LSE: RSG I rml.com.au
8
ASX Announcement
Figure 2: Construction of the Electrostatic Precipitator (ESP), a key component of Roaster Upgrade
Figure 3: Flotation Circuit
The project remains on track and on budget. As per Figure 4, full commissioning is expected in Q3 2026
followed by a ramp-up throughout Q4 2026.
Figure 4: SSCP Timeline
ASX/LSE: RSG I rml.com.au
9
ASX Announcement
Senegal
Mako Operations
Mako gold production for the Quarter was 15,801oz at an AISC of $1,669/oz. The operational
performance for Mako is set out in the table below.
March
2025
Quarter
Units
March
2026
Quarter
December
2025
Quarter
Ore Mined
t
611,465
Mined Grade
g/t
1.76
Ore Processed
t
573,539
603,698
-5%
533,995
Processed Grade
g/t
0.93
1.04
-11%
1.78
Recovery
%
90
91
-1%
92
Gold Poured
oz
15,801
18,755
-16%
27,263
Gold Sold
oz
15,162
19,915
-24%
21,498
0.6
1,669
0.3
1,666
95%
0%
1.0
1,274
Summary
% Change
Mining
Processing
Financials
0
Capital Expenditure
AISC
$m
$/oz
Table 3: Mako Production and Cost Summary
At Mako, the operation delivered a solid Q1 performance in line with expectations. During the quarter, the
plant processed over 574 kt of stockpiled material at an average gold head grade of 0.93 g/t, producing
15,801 oz of gold. As per Figure 5, Mako remains on track for full-year production guidance of 55 - 65
koz with steady Quarterly production levels expected.
Figure 5: 2026 Mako actual gold production (koz) and guidance
ASX/LSE: RSG I rml.com.au
10
ASX Announcement
During the Quarter the AISC was $1,669/oz in line with expectations reflecting continued cost discipline
and operational control. Mako remains on track with full-year AISC guidance of $1,600 - 1,800/oz,
supporting resilient margins and consistent cash flow generation.
Capital expenditure in Q1 was $0.6 million (Q4 2025: $0.3 million) and consisted of replacement parts for
the processing plant.
No material supply disruptions have been experienced in Senegal during Q1. At Mako, which relies on
LFO for both mobile equipment and power generation, fuel storage capacity is maintained at greater than
94%, representing approximately 27 days of operational coverage. Inventories of other consumables and
key reagents generally exceed one month, with the majority exceeding two months. If the current prices
for fuel, approximately 30% higher than originally anticipated, are maintained for the remainder of the
year we expect there to be an increase to AISC of approximately $50/oz for the full-year.
Mako Life Extension Project (MLEP)
MLEP represents a compelling growth opportunity, centered on the potential development of the
Tomboronkoto and Bantaco satellite deposits. Advancing these deposits is expected to extend the mine
life of the Mako Gold Mine and further enhance the long-term value of the operation.
The current combined Mineral Resource Estimates of Tomboronkoto and Bantaco contain over 800 koz
of gold, with possibilities of expansion based on ongoing exploration. There is significant potential at
Tomboronkoto with the orebody remaining open along strike to the west and at depth.
Following internal technical studies, an initial Ore Reserve of 348 koz oz at 1.2g/t Au is at a gold price
assumption of $2,500/oz was declared at Tomboronkoto.
In Q1 $2.9 million was spent on the MLEP, consisting of technical and metallurgical studies and
Relocation Action Plan (RAP) development. The MLEP remains on track and on budget as per Figure 6.
Figure 6: Approximate Timeline for the MLEP
ASX/LSE: RSG I rml.com.au
11
ASX Announcement
Detailed Operating Plan
Technical studies have been carried out that consolidate historical exploration results, updated Mineral
Resource Estimates as at December 2025, mine design, scheduling and metallurgical test work to a level
of confidence considered appropriate for internal planning purposes.
Mining and processing studies support a conventional open pit operation with ore being processed
through the existing Mako plant, subject to targeted plant upgrades. Internal scheduling work indicates
Bantaco is expected to provide initial satellite mill feed ahead of Tomboronkoto (Figure 7), reflecting
permitting and resettlement sequencing, with Tomboronkoto providing the majority of higher-grade feed
once mining commences.
Bantaco oxide ore properties are consistent with Mako oxides so processing plant upgrades are only
required prior to processing Tomboronkoto oxides which have a higher clay content.
Figure 7: Annual mill feed (in tonnes) schedule by source
Based on current schedules, indicatively, the combined MLEP is assessed as capable of supporting
annual gold production of approximately 75 - 85 koz over seven years with indicative gold production
from satellite sources commencing following depletion of existing stockpiles and continuing over the
subsequent mine life, subject to refinement through ongoing optimisation and permitting outcomes.
ASX/LSE: RSG I rml.com.au
12
ASX Announcement
Figure 8: Annual recovered gold ounces (oz) by source
Capital and operating cost estimates were prepared on a combined MLEP basis during the quarter using
detailed cost frameworks at Tomboronkoto, supplemented by high-level estimates for Bantaco pending
further study. On this basis, total pre-production costs for the combined MLEP is estimated at
approximately $125 - 150 million, reflecting process plant modifications, tailings infrastructure,
resettlement and enabling works, road construction and mining establishment costs. The majority of this
is expected in the second half of 2027. Operating cost estimates are expected to be similar to those at
the Mako Mine with the addition of haulage and will continue to be refined as an integrated life-of-mine
plan is progressed. All capital, cost and production parameters remain subject to further optimisation,
permitting approvals and execution planning.
Tomboronkoto
During Q1 2026, key development milestones were successfully achieved at Tomboronkoto, with the final
Environmental & Social Impact Assessment validated by the authorities and the feasibility study
completed. These achievements significantly de-risk the project and position it strongly to support the
forthcoming mining permit application that is being submitted in Q2 2026.
Planning and stakeholder engagement activities to inform the development of the RAP are well underway
and remain ongoing while all required surveys are being finalised. Receipt of the mining permit will provide
the necessary authority to implement the RAP, including the initiation of village relocation once agreement
has been reached with the affected parties. This approach underscores our commitment to regulatory
compliance, transparent community consultation, and responsible project execution.
ASX/LSE: RSG I rml.com.au
13
ASX Announcement
During Q1 2026, the village relocation site was pre-selected and validated with all stakeholders, including
village and state representatives. In Q2 2026, this site selection process will be finalised following the
completion of all required field investigations, including geophysical surveys to identify groundwater
availability, geotechnical characteristics, and sterilisation requirements. Individual household asset
surveys, the relocation entitlement matrix, and public infrastructure designs will also be validated during
Q2 2026.
Formal ESIA studies for the expansion of the existing Mako Mine Process Plant, including a new TSF
and Ore Transport Road between Tomboronkoto and the Mako plant, progressed as planned during Q1
2026. The TSF technical study and detailed engineering commenced during the Quarter and is expected
to be completed by Q3 2026. Detailed engineering for the Mako processing facility is expected to
commence in Q2 2026.
Bantaco
During Q1, strong progress was made across key workstreams, including ongoing metallurgical test work
and technical studies, which remain on track for completion in Q2 2026. Environmental permitting
activities also advanced well, with the ESIA progressing towards submission.
Community engagement activities with the affected communities are also ongoing as part of the
development of a Livelihood Restoration Plan.
Next Steps
Key next steps for the MLEP include:
•
Submission of the Tomboronkoto mining permit application in Q2 and, assuming no major
revisions are required, approval is anticipated in 2027
•
Submission of the ESIA for the Mako plant upgrades, Gambia river bridge and ore transport route
in April 2026 with approval anticipated during Q4 2026
•
Finalisation of Bantaco technical studies are expected towards the end of Q2 2026
•
Submission of Bantaco ESIA in Q2 2026 and validation anticipated in Q3 2026
•
Preparation of all documentation for submission of the Bantaco Mining Permit application in Q3
2026
ASX/LSE: RSG I rml.com.au
14
ASX Announcement
Côte d’Ivoire
Doropo Project
Doropo continues to track strongly towards first gold which is expected in H2 2028. Key milestones were
delivered during Q1, as construction activities are set to accelerate in Q2 2026, positioning the project
for a well-executed build and long-term value creation.
Permitting and Investment Milestones
During Q1, material progress was achieved at the Doropo Project. All key approvals were secured during
the quarter, including issuance of the mining permit in February 2026, signing of the Mining Decree in
March 2026 and announcement of FID on 12 March 2026.
The mining permit is valid for 14 years with the ability to extend. The permit covers a substantial area of
400km², encompassing the main Doropo deposits and several drill-tested mineralised trends.
Contracts and Procurement
During Q1 bids for the EPCM contract were evaluated and post-quarter end Lycopodium Limited were
awarded the EPCM contract.
Key long-lead procurement packages were tendered during FEED, including mills, crushers, oxygen
plant, CIL tanks, thickeners and associated processing equipment, with adjudication substantially
complete and major equipment awards anticipated in Q2 2026.
Early construction-related packages covering camp facilities and the Doropo village were tendered and
progressed to evaluation.
Site Preparation
Site preparation and engineering activities advanced, including completion of geotechnical investigations
and early engineering design for the tailings storage facility, water infrastructure, access roads and
airstrip.
Major earthworks contracts were adjudicated, with early pioneer earthworks awarded and mobilisation
scheduled for April 2026. Water bore drilling contracts were also awarded during the quarter.
Project Team & Organisational Build-Out
Owner’s team was strengthened with the appointment of senior personnel across construction,
procurement, cost control and mining engineering functions.
Land Access & Community Engagement
Land access and compensation activities continued, with land surveys completed, compensation tariffs
agreed and payment mechanisms established. Post-quarter end the compensation payments for early
works areas were substantially completed.
ASX/LSE: RSG I rml.com.au
15
ASX Announcement
Figure 9: Land compensation activities
Planned Activities
During Q2 activities are expected to focus on placing orders for major long-lead items, commencing bulk
earthworks and camp construction, expanding site infrastructure, advancing HV power supply
arrangements and progressing full-scale site development. Upcoming activities include:
Owner’s Team and Studies
•
Continue buildup of the owner’s team
•
Appoint HV power engineer and start HV power supply engineering and early work
Land Access, Acquisition and Crop Compensation
•
Complete compensation for all identified early works areas within the project development
footprint in early April 2026
•
Continue compensation activities for areas outside the early works footprint
Procurement and Fabrication Packages
•
Place orders for long lead items (Mills, Jaw crusher, Apron feeders, CIL tanks and agitators,
Thickener, Oxygen plant, Cyclones, Sewage treatment plant, Cranes and hoists)
•
Commence tender process for remaining equipment (mechanical, electrical, piping and valves)
and steelwork and fabrication packages
•
Commence procurement and hire of site vehicles and mobile equipment
Site Works and Early Construction
•
Commence temporary construction camp upgrade and award contracts for permanent camp
construction
•
Commence site earthworks, including access, plant side, construction camp and water
infrastructure in April 2026
•
Commence drilling and equipping of water bores
ASX/LSE: RSG I rml.com.au
16
ASX Announcement
Figure 10: Groundbreaking starting on site
Figure 11: Ground clearance activities
ASX/LSE: RSG I rml.com.au
17
ASX Announcement
The Doropo project remains on track with the timeline in Figure 12 with first gold expected in H2 2028.
Figure 12 : Doropo Project Timeline
ASX/LSE: RSG I rml.com.au
18
ASX Announcement
Côte d’Ivoire Exploration
ABC Project
The ABC Project is a greenfield exploration project located in western Cote d'Ivoire. Resolute has four
exploration permits granted around the ABC Project with two further permit applications.
Over Kona Central and South deposits there is a NI 43-101-compliant Inferred MRE of 2.16 Moz grading
0.9 g/t Au contained within the Kona permit.
Figure 13: Permit and Prospect Locations at the ABC Project
Exploration activity during Q1 focused on drilling programs planned to expand the Mineral Resources at
the Kona deposits. Furthermore, a scoping study on the ABC Project, based on the existing MRE, was
advanced during the period and is expected in Q2 2026.
Drilling successfully advanced efforts to extend known mineralisation at both Kona South and Kona
Central, along strike to the north and south of the deposits. A total of 64 RC holes for 11,000m were
completed during the March quarter with drilling at both areas reinforcing the scale and continuity of the
mineralised system.
Drilling progressed strongly during the quarter, where activity ramped up to five rigs toward period end to
accelerate delineation and rapidly expand the mineralised footprint, positioning the project for continued
resource growth.
ASX/LSE: RSG I rml.com.au
19
ASX Announcement
Results from the first 40 holes demonstrate wide intervals of gold mineralisation across the majority of
drilling completed to date, reinforcing the scale and continuity of the system. Key standout intersections
include:
•
KNRC0499 – 73m @ 0.8g/t Au from 2m
•
KNRC0500 – 80m @ 0.4g/t Au from 88m
•
KNRC0501 – 23m @ 1g/t Au from 6m
•
KNRC0506R – 35m @ 0.9 and 21m @ 1.2g/t
•
KNRC0508 – 10m @ 1.9g/t Au from 217m
•
KNRC0512 – 31m @ 1g/t from 151m
The majority of the results returned to date are from Kona South which is higher grade than Kona Central.
The drill intersections clearly confirm the along strike extensions of the gold mineralisation to the north
and south of Kona South.
All reported drill intersections are located outside the current Mineral Resource block models, highlighting
clear potential for a meaningful increase in the existing resource base and underpinning a compelling
growth opportunity.
ASX/LSE: RSG I rml.com.au
20
ASX Announcement
Figure 14: Kona South Plan with drillhole locations
New drilling north of Kona South has delivered wide zones of mineralisation, extending the zones by
500m to the north, highlighting potential continued resource expansion.
ASX/LSE: RSG I rml.com.au
21
ASX Announcement
Figure 15: Kona South cross section at 967950N
The accelerated drilling program will continue throughout 2026 to build the Mineral Resource Inventory
of the ABC Project. An updated Mineral Resource Estimate is planned to be announced in H2 2026.
A scoping study is underway on the existing Kona MRE, with results due for release in Q2 2026, marking
an important step in advancing the project’s development pathway.
La Debo Project
The La Debo Project, located in southern Côte d’Ivoire approximately 280 km west of Abidjan, hosts an
Inferred Mineral Resource of 17.6Mt at 1.14 g/t Au for 643 koz of contained gold (0.5 g/t cut-off) across
the G3S and G3N prospects, providing a strong foundation for future growth.
A diamond drilling program commenced in March 2026 at G3S, aimed at expanding the existing Mineral
Resource. Drilling last year identified a coherent linear zone of high-grade mineralisation at the deepest
levels of G3S highlighting compelling potential for the development of a future underground operation.
This drilling program aims to drill out a panel of gold mineralisation over a strike length of 600m which
may form the basis of an underground operation.
ASX/LSE: RSG I rml.com.au
22
ASX Announcement
Drilling is progressing well, with results expected to be released in the second half of 2026, providing
near-term catalysts for resource growth and project advancement. 13,000m of drilling is planned for the
remainder of 2026.
Figure 16: La Debo Project Permits and Prospect Locations
Subject to positive drilling results at depth at G3S, La Debo has the potential to advance its development
stage, with further technical and strategic updates planned for the second half of 2026. This work will
support a comprehensive assessment of the project’s potential and help identify broader growth
opportunities in the region.
ASX/LSE: RSG I rml.com.au
23
ASX Announcement
Doropo Exploration
Exploration drilling within the Doropo Mining Permit is set to commence in Q2 2026 targeting both the
Vako area and Kilosegui - see Figure 17.
Kilosegui represents a potential mineral resource expansion opportunity, with a 6km strike length and
mineralisation remaining open at depth along its entire strike length. The initial strategy is to expand the
Kilosegui Mineral Resources at depth but within the top 200m.
Historical exploration by Centamin identified a broad, high-grade gold-in-soil anomaly along the Vako
Shear Zone, with initial follow-up drilling returning encouraging early-stage results. However, there was
no further work carried out at the Vako Shear Zone.
Resolute plans to carry out a systematic work program at Doropo, commencing with auger drilling to
identify the source of the gold anomalies, followed by a focused RC drilling campaign to test and delineate
the underlying mineralisation. Detailed exploration planning is underway with up to 30,000m of drilling
potentially planned.
Figure 17: Map of deposits and prospects at Doropo
ASX/LSE: RSG I rml.com.au
24
ASX Announcement
Guinea
Strategic Partnership with Nimba Mining Company
In March the Company signed an MoU with the state-owned company Nimba Mining Company (NMC).
This strategic partnership demonstrates the Government's recognition of and the support for Resolute's
growth plans in Guinea.
The partnership will focus on jointly assessing mineral resources, conducting comprehensive geological
studies, and developing strategic frameworks for potential large-scale gold production operations. The
MoU aligns with Resolute's strategy of building a pipeline of high-quality growth opportunities in
established West African gold jurisdictions. Moreover, it complements Resolute’s other exploration
activities in Guinea including a reconnaissance authorisation covering 83 km2 within the Siguiri Basin.
The next steps of the MoU involve Resolute and NMC completing a preliminary assessment of areas of
interest and forming a joint team to review these, within the next 90 days following signing.
Planned Activities
At Barama, initial soil geochemistry results from the reconnaissance authorisation are expected in Q2
2026. Subject to results, the Company plans to undertake tighter-spaced (infill) soil sampling to refine
and prioritise identified anomalies for follow-up.
In parallel, Resolute will continue to assess additional licence opportunities and advance its business
development activities throughout Q2 2026.
ASX/LSE: RSG I rml.com.au
25
ASX Announcement
Mineral Resources and Ore Reserves Statement
During the Quarter Resolute released its Mineral Resources and Ore Reserves statement as of 31
December 2025.
Ore Reserves
Total Ore Reserves increased by 55% to 6.8 Moz Au with the addition of Ore Reserves at Doropo (Côte
d’Ivoire) and Tomboronkoto (Senegal) offsetting mining depletion in Mali and Senegal.
Proved
As at December 2025
Tonnes
g/t Au
(000s)
Probable
oz
Tonnes
Total Reserves
g/t Au
oz
Tonnes
g/t Au
oz
(000s)
(000s)
(000s)
(000s)
Mali
808
1.50
39
49,315
2.40
3,847
50,123
2.40
(000s)
3,885
Senegal
3,896
0.90
118
9,076
1.20
348
12,972
1.10
467
Côte d’Ivoire
1,400
1.60
73
57,700
1.30
2,424
59,100
1.30
2,497
Managed Ore Reserves
6,105
1.20
230
116,091
1.80
6,619
122,196
1.70
6,849
Table 4: Ore Reserves (100% Basis)
Mali
At Syama, Underground Ore Reserves decreased by 235 koz Au, consistent with expectations,
reflecting mining depletion and updated modifying factors based on a $2,300/oz gold price assumption.
Stockpile Ore Reserves declined as material was processed, with higher sulphide depletion in 2025 due
to underground mining disruptions, while oxide stockpiles reduced broadly in line with expectations;
further oxide depletion is anticipated ahead of commissioning of the SSCP in H2 2026.
Ore Reserves at Tabakoroni Underground were unchanged. Ore Reserves at the Syama Satellite
Deposits increased by 83 koz to 1.6 Moz Au following completion of a new pit optimisation, with Syama
North underpinning the SSCP and the long-term future of the Syama operation.
Senegal
At Mako, Ore Reserves decreased by 108 koz Au due to mining depletion, following the completion of
open pit mining in June 2025 and the commencement of stockpile processing in H2 2025. Remaining
Proven Ore Reserves total 108 koz Au at 0.9 g/t Au, with stockpile processing expected to continue until
the end of 2027.
An initial Ore Reserve of 348 koz Au at 1.2 g/t Au has been declared for Tomboronkoto based on a
$2,500/oz gold price assumption. Further optimisation studies at Tomboronkoto and Bantaco are
planned as part of the Mako Life Extension Project.
Cote d'Ivoire
Following the updated DFS completed in 2025 the Doropo Ore Reserves total 2.5 Moz Au grading 1.3
g/t using a gold price assumption of $1,950/oz.
ASX/LSE: RSG I rml.com.au
26
ASX Announcement
Mineral Resources
Total Mineral Resources increased by 60% to 17.6 million gold (Au) ounces (Moz) with the acquisition
of the Doropo and ABC projects (Côte d’Ivoire) and exploration success at Bantaco (Senegal) and La
Debo (Côte d’Ivoire).
Measured
As at
December
2025
Tonnes g/t Au
Mali
29,227
Senegal
Côte d’Ivoire
Guinea
Managed
Mineral
Resources
Indicated
oz
Tonnes
(000s)
(000s)
2.90
2,683
48,398
3,947
0.90
120
1,550
1.60
78
0
0.00
34,724
2.60
(000s)
g/t Au
Inferred
oz
Tonnes g/t Au
Total Resources
oz
Tonnes
(000s)
(000s)
g/t Au
oz
(000s)
(000s)
(000s)
3.10
4,751
31,291
1.70
1,668
108,916
2.60
9,101
16,894
1.30
687
6,869
1.00
224
27,709
1.20
1,031
95,200
1.20
3,601
106,999
1.20
3,483
203,749
1.20
7,162
0
0
0.00
0
6,625
0.90
343
6,625
0.90
343
2,881
160,492
1.80
9,038
151,784
1.20
5,718
347,000
1.60
17,637
Table 5: Mineral Resources (100% Basis)
Mali
Mineral Resources at the Syama Underground mine decreased by approximately 680 koz Au, reflecting
mining depletion, an updated resource estimate and revised RPEEE (Reasonable Prospects For
Eventual Economic Extraction) inputs. The Syama North Mineral Resource decreased by approximately
50 koz to 3.3 Moz Au due to mining depletion and revised RPEEE inputs. Mineral Resources at
Tabakoroni Underground were unchanged.
Senegal
Mineral Resources at Mako, including stockpiles, decreased by approximately 130 koz Au in line with
mining depletion, with no further additions expected following completion of open pit mining and the
commencement of stockpile processing.
Mineral Resources at Tomboronkoto increased in 2025 due to reporting at a lower cut-off grade of 0.5
g/t Au within a $2,950/oz optimised pit shell, increasing to 444 koz Au at 1.3 g/t Au (2024: 377 koz at 1.7
g/t Au). At Bantaco the Mineral Resource was updated to 365 koz Au at 1.0 g/t Au.
Cote d'Ivoire
Mineral Resource additions reflect the acquisition of the Doropo and ABC projects and the declaration
of an initial Mineral Resource at La Debo.
At Doropo, an updated Mineral Resource Estimate released in September 2025, based on a $3,000/oz
gold price assumption, increased total Mineral Resources to 4.4 Moz Au, a 1 Moz Au increase from
2023, with approximately 84% classified as Measured and Indicated.
At the ABC Project, Mineral Resources total 2.2 Moz Au at the Kona Central and South deposits, with
further exploration and a Scoping Study planned during 2026.
An initial Mineral Resource was declared at La Debo in November 2025 of 643 koz Au at 1.14 g/t Au,
with further drilling planned during 2026.
ASX/LSE: RSG I rml.com.au
27
ASX Announcement
Financial Highlights and Balance Sheet Activities
Quarterly Net Cash Movements (US$ million)
*Included in Operating Cash flows are $26.9 million of royalties
Figure 18: Q1 2026 Net Cash Movements
In Q1 gold sales of 69,352 oz were achieved at an average realised gold price of $4,858/oz (Q4:
$4,023/oz), with all gold being sold at spot prices. The strong gold price environment helped the Company
generate an operating cashflow of $119.8 million in Q1.
For Q1 there was a working capital outflow of $3.1 million (Q4 2025: $29.0 million inflow) The working
capital outflow was due to a reduction in payables that were settled in the normal course of business.
The VAT paid in Q1 in Mali and Senegal was $8.7 million (Q4 2025: $12.3 million). During the Quarter
$4.3 million of VAT mandates were approved by the Senegalese tax authorities and will be used to settle
payables in Q2. Resolute continues to engage with local governments to settle these amounts. In Q2
Resolute expects considerable income tax payments in Mali and Senegal of approximately $50 million.
EBITDA for the three months ending 31 March 2026 was $202.9 million (Q4 2025: $104.9 million)
reflecting $337.6 million of revenue (Q4 2025: $201.5 million) driven by the significant increase in gold
prices in the quarter as well the impact of the increase of gold sales in the quarter.
Exploration Expenditure
Total Group exploration spend, including capital and operating expenditure, in Q1 was $5.3 million (Q4
2025: $5.6 million), with drilling programs continuing in Senegal ($1.1 million), Côte d’Ivoire ($3.7 million)
and Mali ($0.5 million). Exploration spend remains on track with guidance ($15 - 25 million).
ASX/LSE: RSG I rml.com.au
28
ASX Announcement
Net Cash Summary
Net cash (including bullion) at 31 March 2026 was $315.4 million, increasing from the $209.0 million net
cash position at 31 December 2025.
Total borrowings at 31 March 2026 were $12.2 million (Q4 2025: $57.0 million) which includes in-country
overdraft facilities in Senegal of $2.2 million, used to optimise working capital, as well as $10.0 million for
in-country equipment financing. Cash, cash equivalents and bullion increased by $106.4 million in the
Quarter to $315.4 million (Q4 2025: $209.0 million) including $31.4 million that was received from the
sale of Resolute's stake in Loncor Gold. The Company has available liquidity of approximately $425.0
million (including $99.6 million bullion on hand) as at 31 March 2026.
As at 31 March 2026 the receivable for the Ravenswood promissory note was approximately $52 million.
The promissory note has an annual coupon of 12% with interest being capitalised and is to be paid to
Resolute upon maturity. The promissory note maturity is 31 December 2027 but may be repaid early on
future Ravenswood financings, liquidity event(s), or excess cash from Ravenswood.
Financing Updates
Resolute intends to use its existing balance sheet and operating cash flows to progress Doropo into
construction. The Company continues to consider a range of funding options to support the construction
of the Doropo project.
ASX/LSE: RSG I rml.com.au
29
ASX Announcement
Guidance
Resolute remains on track for its full-year production guidance of 250,000 – 275,000 oz.
Group AISC of $2,000 - 2,200/oz (at a gold price assumption of $4,000/oz) is maintained however is
subject to change at current elevated gold prices and higher fuel costs. For every $100/oz increase in
gold price we anticipate a $20/oz increase in Group AISC. If prices for fuel persist at current levels we
expect an impact to the Group's full-year AISC.
Year to Date
Guidance
Gold Production
(oz)
AISC ($/oz)
Gold Production
(oz)
AISC ($/oz)
Syama
43,802
2,227
195,000 – 210,000
1,950 – 2,150
Mako
15,801
1,669
55,000 – 65,000
1,600 - 1,800
Total Group
59,603
2,210
250,000 – 275,000
2,000 – 2,200
Total group AISC includes corporate costs
Table 6: Summary of year-to-date performance and full-year production and cost guidance
Total Group capital expenditure, inclusive of Doropo and exploration, is expected to be between $310 360 million in 2026. Administration and other corporate expenditure is expected to be approximately $25
million.
Doropo capital expenditure is expected to be weighted 75% to the second half of 2026.
Year to Date Spend
Guidance
Syama
12.6
70 - 85
SSCP
8.0
40
Mako
0.6
5
MLEP
2.9
10 - 15
Doropo
4.2
170 - 190
Exploration
5.1
15 - 25
Total
33.4
310 - 360
(US$ million)
Table 7: Summary of 2026 capital expenditure guidance
ASX/LSE: RSG I rml.com.au
30
ASX Announcement