SUMMARY The Board is pleased to announce that, on 23 October 2026, the Consortium and Dongguan City Appearance and Environmental Sanitation Center entered into the Preliminary Concession Agreement, in respect of the investment, financing,…
SUMMARY
The Board is pleased to announce that, on 23 October 2026, the Consortium and Dongguan
City Appearance and Environmental Sanitation Center entered into the Preliminary
Concession Agreement, in respect of the investment, financing, construction, operation
and maintenance of the Project. The Project will be implemented by way of a build-ownoperate-transfer (BOOT) model. The Consortium will establish a new company as the
Project Company to undertake the Project and will enter into the proposed Shareholders’
Agreement shortly before the incorporation of the Project Company. Following its
incorporation, the Project Company will enter into the formal Concession Agreement with
Dongguan City Appearance and Environmental Sanitation Center and assume the relevant
rights and obligations of the Consortium under the Preliminary Concession Agreement.
1
The total investment amount for Phase I of the Project is expected to be approximately
RMB2,252,035,800 (equivalent to approximately HKD2,631,503,800), which includes
the expected registered capital of the Project Company amounting to approximately
RMB675,610,700 (equivalent to approximately HKD789,451,100). The total investment
amount for Phase II kitchen waste treatment facilities will be determined by the Project
Company at the relevant time. EEP China will make a capital contribution of approximately
RMB537,110,500 (equivalent to approximately HKD627,613,600) into the Project
Company as a portion of the registered capital of the Project Company. Upon completion
of the capital contribution, EEP China, CSCEC Third Engineering and Guangzhou WeTech
shall hold 79.5%, 20% and 0.5% equity interests in the Project Company, respectively.
Following its incorporation, the Project Company will be accounted for as a subsidiary of
the Company with its financial results to be consolidated into the Company’s consolidated
financial statements.
During the Concession Period, the Project Company will be responsible for the investment,
financing, construction, operation and maintenance of the Project and the provision of
municipal solid waste treatment services and kitchen waste treatment services, and will be
entitled to receive municipal solid waste treatment service fees, kitchen waste treatment
service fees, on-grid tariff income from waste-to-energy generation and income from
relevant resource utilisation products.
LISTING RULES IMPLICATIONS
As the highest applicable percentage ratio calculated with reference to Rule 14.07 of
the Listing Rules exceeds 5% but is less than 25%, the transaction contemplated under
the Preliminary Concession Agreement, the proposed Shareholders’ Agreement and the
proposed Concession Agreement constitutes a discloseable transaction of the Company
under Chapter 14 of the Listing Rules, and is subject to the reporting and announcement
requirements but exempt from the Shareholders’ approval requirement under the Listing
Rules.
SUMMARY
The Board is pleased to announce that, on 23 October 2026, the Consortium and Dongguan
City Appearance and Environmental Sanitation Center entered into the Preliminary
Concession Agreement, in respect of the investment, financing, construction, operation and
maintenance of the Project. The Project will be implemented by way of a build-own-operatetransfer (BOOT) model.
2
The Consortium will establish a new company as the Project Company to undertake the
Project and will enter into the proposed Shareholders ’ Agreement shortly before the
incorporation of the Project Company. Following its incorporation, the Project Company
will enter into the formal Concession Agreement with Dongguan City Appearance and
Environmental Sanitation Center and assume the relevant rights and obligations of the
Consortium under the Preliminary Concession Agreement.
THE PROJECT AND THE CONCESSION ARRANGEMENTS
(1)
The Preliminary Concession Agreement and the proposed Concession Agreement
On 23 October 2026, the Consortium (comprising EEP China, CSCEC Third
Engineering and Guangzhou WeTech) and Dongguan City Appearance and
Environmental Sanitation Center entered into the Preliminary Concession Agreement.
Pursuant to the Preliminary Concession Agreement, the Consortium shall establish
the Project Company within a prescribed period after the signing of the Preliminary
Concession Agreement, and the Project Company shall enter into the formal Concession
Agreement with Dongguan City Appearance and Environmental Sanitation Center within
a prescribed period after its establishment.
(2)
Overview of the Project
The Project involves the investment, financing, construction, operation and maintenance
of municipal solid waste and kitchen waste treatment facilities, as well as the supply of
green electricity to the power grid in Dongguan City.
The Project will be located in Dongguan City. The Project is designed to have a
municipal solid waste treatment capacity of 3,000 tonnes per day, and will also include
kitchen waste treatment facilities with an aggregate treatment capacity of 500 tonnes per
day. Phase I of the Project will construct, inter alia , facilities with a designed municipal
solid waste treatment capacity of 3,000 tonnes per day and a designed kitchen waste
treatment capacity of 300 tonnes per day, while Phase II will construct, inter alia ,
facilities with a designed kitchen waste treatment capacity of 200 tonnes per day.
3
During the Concession Period, the Project Company will provide municipal solid waste
treatment services and kitchen waste treatment services, and will be entitled to receive
municipal solid waste treatment service fees, kitchen waste treatment service fees, ongrid tariff income from waste-to-energy generation and income from relevant resource
utilisation products.
As the Project has not yet commenced, no book value has been generated in respect of
the Project, and no profit is attributable to the Project.
(3)
Concession model
The Project will be implemented under the build-own-operate-transfer (BOOT) model.
During the Concession Period, the Project Company will be granted concession rights
to invest in, finance, construct, operate and maintain the Project, and to provide
municipal solid waste treatment services and kitchen waste treatment services within the
concession service scope.
The Concession Period is set at 31 years (including the preliminary phase and
construction period). The Concession Period shall commence from the effective date of
the formal Concession Agreement and end on the transfer date. The preliminary phase
and construction period shall not exceed 2.25 years (27 months), and the remaining
period shall be the operation period. Upon expiry of the Concession Period, the
Project Company shall transfer the Project facilities to Dongguan City Appearance and
Environmental Sanitation Center or the municipal government’s designated entity at nil
consideration.
(4)
The Project Company
The Project Company will be responsible for the implementation of the Project,
including investment, financing, construction, operation and maintenance.
The Project Company shall be incorporated by the Consortium and funded by the
Consortium members in accordance with the equity proportions agreed to in the
proposed Shareholders ’ Agreement. The registered capital of the Project Company
is expected to be approximately RMB675,610,700 (equivalent to approximately
HKD789,451,100), representing 30% of the total investment amount of Phase I of the
Project.
4
(5)
The investment amount of the Project and the financing obligations
The total investment amount for Phase I of the Project is expected to be approximately
RMB2,252,035,800 (equivalent to approximately HKD2,631,503,800), which includes
the expected registered capital of the Project Company amounting to approximately
RMB675,610,700 (equivalent to approximately HKD789,451,100). The total investment
amount for Phase II kitchen waste treatment facilities will be determined by the Project
Company at the relevant time. At that time, the Project Company shall be responsible for
the investment, construction and operation of Phase II.
The difference between the investment amount required for Phase I of the Project and
the registered capital of the Project Company will be financed by the Project Company,
which shall be the financing entity, through financing methods including bank loans and
shareholder loans.
The total investment amount of Phase I of the Project was determined after arm ’s
length negotiation among the Consortium with reference to the complexity and size
of the Project and the projected municipal solid waste treatment service fees, kitchen
waste treatment service fees, on-grid tariff income from waste-to-energy generation and
income from relevant resource utilisation products to be received.
As at the date of this announcement, the total investment amount in relation to Phase
II of the Project remains subject to determination. The Company will make further
announcement(s) as and when appropriate and in accordance with the Listing Rules upon
the determination of the total investment amount for Phase II of the Project.
(6)
Performance bonds
The Consortium and/or the Project Company shall provide performance bonds in relation
to the Project by bank letter of guarantee, comprising:
(i)
a construction period performance bond of RMB60,000,000, to be submitted
within 25 Business Days after the signing of the formal Concession Agreement.
The construction period performance bond bank letter of guarantee shall be
released or discharged within 15 Business Days after the Project Company
formally commences operation, the construction period assessment has been
completed and any assessment-linked deduction from the performance bond has
been completed;
5
(ii)
an operation period performance bond of RMB20,000,000, to be submitted within
one month before commencement of the operation period. The operation period
performance bond bank letter of guarantee shall be released or discharged within
15 Business Days after the transfer date; and
(iii) a transfer performance bond of RMB60,000,000, to be submitted before 12
months of the transfer of the Project. The transfer performance bond bank letter of
guarantee shall be released or discharged after the transfer of the Project have been
completed and upon expiry of the quality warranty period (being 2 years after the
transfer date).
Such performance bonds shall be issued by commercial banks or other financial
institutions recognised by Dongguan City Appearance and Environmental Sanitation
Center and shall be irrevocable and payable on demand if provided in the form of bank
letter of guarantee.
THE PROPOSED SHAREHOLDERS’ AGREEMENT
The principal terms of the proposed Shareholders’ Agreement are set out below:
(1)
(2)
Parties
(a)
EEP China;
(b)
CSCEC Third Engineering; and
(c)
Guangzhou WeTech.
Formation of Project Company
EEP China shall take the lead, with the cooperation of CSCEC Third Engineering
and Guangzhou WeTech, to complete the incorporation registration procedures for
the Project Company within 30 days after the signing of the proposed Shareholders’
Agreement.
The Project Company shall be established as a limited liability company with a longterm operating period commencing from the date of issuance of its business licence.
6
(3)
Purpose of the Project Company
The Project Company will be established for the purpose of undertaking the Project,
including operating municipal solid waste treatment services, power generation,
transmission and power supply or distribution businesses, and kitchen waste treatment.
(4)
Capital Contribution and Shareholding
The registered capital of the Project Company is expected to be approximately
RMB675,610,700 (equivalent to approximately HKD789,451,100), of which:
(i)
EEP China shall contribute in cash RMB537,110,500 (equivalent to approximately
HKD627,613,600), accounting for 79.5% of the registered capital of the Project
Company;
(ii)
CSCEC Third Engineering shall contribute in cash RMB135,122,100 (equivalent to
approximately HKD157,890,200), accounting for 20% of the registered capital of
the Project Company; and
(iii) Guangzhou WeTech shall contribute in cash RMB3,378,100 (equivalent to
approximately HKD3,947,300), accounting for 0.5% of the registered capital of the
Project Company.
The Parties shall contribute their respective capital contributions within 15 Business
Days after receipt of a written capital contribution payment notice from the Project
Company, according to the Project’s construction progress and actual funding needs,
and all subscribed capital contributions shall be fully paid within two years from the
establishment of the Project Company.
The capital contribution by EEP China into the Project Company was determined after
arm’s length negotiation among the Consortium with reference to the expected registered
capital of the Project Company (being 30% of the total investment amount of Phase
I of the Project), the Project’s actual funding needs, and the Consortium’s respective
shareholding percentages in the Project Company.
The capital contribution to be made by EEP China will be funded by the Group ’s internal
resources.
7
(5)
Corporate Governance
Upon incorporation of the Project Company, EEP China, CSCEC Third Engineering
and Guangzhou WeTech shall hold 79.5%, 20% and 0.5% equity interests in the Project
Company, respectively.
Subject to the terms of the proposed Shareholders’ Agreement, certain matters of the
Project Company will require the approval of shareholders representing more than fivesixths of the voting rights, including but not limited to (i) amendments to the articles of
association; (ii) increases or decreases in registered capital; (iii) the company’s merger,
division, dissolution, or change of corporate form; and (iv) material matters involving
public interest and public safety.
The board of directors of the Project Company shall consist of three directors, of whom
two shall be nominated by EEP China and one shall be nominated by CSCEC Third
Engineering, and the chairman of the board shall be elected by the board from the
directors nominated by EEP China.
(6)
Management of the Project Company
The Project Company shall have one general manager appointed by EEP China and
four deputy general managers, of whom three shall be appointed by EEP China and one
shall be appointed by CSCEC Third Engineering, with such deputy general manager
concurrently serving as the chief financial officer of the Project Company.
(7)
Profit Sharing
After the Project Company has made up losses and appropriated statutory and
discretionary reserves in accordance with applicable laws and as required by relevant
internal policies, its remaining after-tax profits shall be distributed among the
shareholders in proportion to their respective paid-up capital contributions.
8
REASONS FOR AND BENEFITS OF ENTERING INTO THE
PRELIMINARY CONCESSION AGREEMENT, THE PROPOSED
SHAREHOLDERS’ AGREEMENT, THE PROPOSED CONCESSION
AGREEMENT AND UNDERTAKING THE PROJECT
The Project is a waste-to-energy and integrated waste treatment project within the Group’s
principal businesses. The entering into of the Preliminary Concession Agreement and
undertaking of the Project are expected to further strengthen the Group’s market presence
in Guangdong Province and the Guangdong-Hong Kong-Macao Greater Bay Area, enhance
the Group’s project portfolio in the environmental protection sector and generate sustainable
returns for the Shareholders.
The Directors (including the independent non-executive Directors) consider that the terms
of the Preliminary Concession Agreement, the proposed Shareholders’ Agreement and the
proposed Concession Agreement are fair and reasonable and in the interests of the Company
and the Shareholders as a whole.
INFORMATION OF THE PARTIES
The Company
The Company is the largest environmental enterprise in China, a leading player in Asia’s
environmental protection industry, the world ’s largest waste-to-energy investor and
operator, and a world-renowned environmental group. As a pioneering one-stop integrated
environmental solution provider in China, the Company focuses on three major areas: solid
waste, water-related business and clean energy. Its main businesses encompass waste-to
energy and integrated waste treatment, integrated biomass utilisation, hazardous and solid
waste treatment, new energy, environmental remediation, water environment management,
equipment manufacturing, waste sorting, integrated environmental sanitation, resource
recycling, zero-waste city development, research and development relating to green
technologies, ecological and environmental planning and designing, as well as environmental
protection industrial parks. The Company operates in more than 220 locations across 25
provinces, autonomous regions, municipalities and a special administrative region in China, as
well as in 20 overseas markets, including Germany, Poland, Vietnam and Uzbekistan.
9
EEP China
EEP China is a company established in the PRC with limited liability and a wholly-owned
subsidiary of the Company. Its businesses encompass waste-to-energy, food and kitchen
waste treatment, leachate treatment, fly ash treatment, methane-to-energy, sludge treatment
and disposal, construction and decoration waste treatment, development of environmental
protection industrial parks, integrated urban services, resource utilisation and recycling, as
well as technical consultancy and engineering design relating to environmental protection.
CSCEC Third Engineering
CSCEC Third Engineering was established in the PRC with limited liability and is principally
engaged in building construction, infrastructure investment and construction and real estate
development. CSCEC Third Engineering is an indirectly wholly-owned subsidiary of China
State Construction Engineering Corporation Limited( 中國建築股份有限公司), a joint stock
limited company established in the PRC with limited liability, the shares of which are listed
on the Shanghai Stock Exchange (Shanghai stock code: 601668).
Guangzhou WeTech
Guangzhou WeTech was established in the PRC with limited liability and is principally
engaged in comprehensive engineering and technical services centered on the energy and
environmental protection sectors. To the best of the Directors’ knowledge, information and
belief, having made all reasonable enquiries, Guangzhou WeTech is owned as to 54%, 40%,
3% and 3% by He Weicai( 何偉才), Chen Boning( 陳柏寧), Liu Hong( 劉紅)and Wu
Liang( 吳亮), respectively.
Dongguan City Appearance and Environmental Sanitation Center
Dongguan City Appearance and Environmental Sanitation Center is a governmental authority
under the Dongguan Municipal People’s Government.
To the best of the Directors’ knowledge, information and belief, having made all reasonable
enquiries, each of CSCEC Third Engineering, Guangzhou WeTech and Dongguan City
Appearance and Environmental Sanitation Center and their respective ultimate beneficial
owners are third parties independent of the Company and its connected persons.
10
LISTING RULES IMPLICATIONS
As the highest applicable percentage ratio calculated with reference to Rule 14.07 of the
Listing Rules exceeds 5% but is less than 25%, the transaction contemplated under the
Preliminary Concession Agreement, the proposed Shareholders’ Agreement and the proposed
Concession Agreement constitutes a discloseable transaction of the Company under Chapter
14 of the Listing Rules, and is subject to the reporting and announcement requirements but
exempt from the Shareholders’ approval requirement under the Listing Rules.
DEFINITIONS
The following expressions shall have the meanings set out below unless the context requires
otherwise:
“Board”
the board of Directors of the Company
“Business Day(s)”
any day (excluding a statutory rest day and statutory holiday
or public holiday in the Chinese Mainland) on which
institutions generally work
“Company”
China Everbright Environment Group Limited, a company
incorporated in Hong Kong with limited liability, whose
shares are listed on the Main Board of the Stock Exchange
(Stock Code: 257)
“Concession Agreement”
the concession agreement to be entered into between the
Project Company and Dongguan City Appearance and
Environmental Sanitation Center in relation to the Project
“Concession Period”
the concession period of the Project pursuant to the
Concession Agreement
“connected person(s)”
has the meaning ascribed to it in the Listing Rules
“Consortium”
a consortium comprising of EEP China, CSCEC Third
Engineering and Guangzhou WeTech
11
“CSCEC Third
Engineering”
China Construction Third Engineering Bureau Group Co.,
Ltd.*( 中建三局集團有限公司), a company incorporated
in the PRC with limited liability
“Director(s)”
the directors of the Company
“Dongguan City”
Dongguan City, Guangdong Province, the PRC
“Dongguan City
Dongguan City Appearance and Environmental Sanitation
Center*( 東莞市市容環衛中心), a governmental authority
authorised by the Dongguan Municipal Government of
Guangdong Province to act as the implementation agency for
the Project
Appearance and
Environmental Sanitation
Center”
“EEP China”
Everbright Environmental Protection (China) Limited*( 光
大環保( 中國)有限公司), a company incorporated in the
PRC with limited liability and a wholly-owned subsidiary of
the Company
“Group”
the Company and its subsidiaries
“Guangzhou WeTech”
Guangzhou WeTech Engineering Co., Ltd.*( 廣州華科工程
技術有限公司), a company incorporated in the PRC with
limited liability
“HKD”
Hong Kong dollars, the lawful currency of Hong Kong
“Hong Kong”
the Hong Kong Special Administrative Region of the PRC
“Listing Rules”
the Rules Governing the Listing of Securities on the Stock
Exchange
“percentage ratio(s)”
has the meaning ascribed to it under the Listing Rules
12
“PRC”
the People’s Republic of China
“Preliminary Concession
Agreement”
the preliminary concession agreement dated 23 October
2026 entered into between the Consortium and Dongguan
City Appearance and Environmental Sanitation Center in
relation to the Project
“Project”
Dongguan Southeast Environmental Energy Project*( 東
莞市東南部環保熱電廠項目), involving the investment,
financing, construction, operation and maintenance of the
municipal solid waste and kitchen waste treatment facilities
in Dongguan City, details of which are set out in the section
headed “The Project and the Concession Arrangements” in
this announcement
“Project Company”
a company to be incorporated with limited liability under
PRC law pursuant to the Preliminary Concession Agreement
for the purpose of undertaking the Project
“RMB”
Renminbi, the lawful currency of the PRC
“Share(s)”
the shares of the Company
“Shareholder(s)”
holder(s) of Share(s) in the Company
“Shareholders’ Agreement”
the shareholders ’ agreement to be entered into by EEP
China, CSCEC Third Engineering and Guangzhou WeTech in
relation to the Project Company
“Stock Exchange”
The Stock Exchange of Hong Kong Limited
“subsidiary(ies)”
has the meaning ascribed to it under the Listing Rules
13
“%”
per cent
By order of the Board
China Everbright Environment Group Limited
Wang Silian
Chairman of the Board
Hong Kong SAR of China, 23 October 2026
In this announcement, the English names of PRC government authorities or entities are
translations of their Chinese names and included herein for identification purpose only. In the
event of any inconsistency, the Chinese names shall prevail.
For the purpose of this announcement, unless otherwise specified, the conversion of RMB
into HKD is based on the exchange rate from RMB1.00 to HKD1.1685. The exchange rate is
adopted for illustration purpose only and does not constitute a representation that any amounts
have been, could have been, or may be, exchanged at this rate or any other rate at all.
As at the date of this announcement, the Board comprises: (i) an Executive Director,
namely Mr. Wang Silian (Chairman of the Board); (ii) two Non-executive Directors, namely
Mr. Kang Guoming and Ms. Qu Li; and (iii) three Independent Non-executive Directors,
namely Mr. Fan Yan Hok, Philip, Ms. Li Shuk Yin, Edwina and Mr. Fok Kai Man.