Proposed Capital Raising Admin-RKH 2026-08-27T10:09:33+01:0027 August 2026| Rockhopper Exploration plc (“Rockhopper” or the “Company”) Proposed Capital Raising Placing of New Ordinary Shares to raise approximately US$180 million Launch of Open…
Proposed Capital Raising
Admin-RKH
2026-08-27T10:09:33+01:0027 August 2026|
Rockhopper Exploration plc
(“Rockhopper” or the “Company”)
Proposed Capital Raising
Placing of New Ordinary Shares to raise approximately US$180 million
Launch of Open Offer
Further to the Company’s announcement on 24 August 2026, Rockhopper Exploration plc (AIM: RKH), the oil and gas company with key interests in the North Falkland Basin, is pleased to announce its intention to raise approximately US$180 million (approximately £132.4 million), before expenses via a placing of New Ordinary Shares at an issue price (the “Issue Price”) of 70 pence per New Ordinary Share (the “Placing”) alongside an open offer of New Ordinary Shares at the Issue Price to raise up to approximately US$20 million (c. £14.4 million) (the “Open Offer”) (together, the “Capital Raising”).
The Issue Price represents a discount of approximately 4.9 per cent. to the volume-weighted average price of 73.5781 pence per Existing Ordinary Share for the 30-day period ended 21 August 2026.
Canaccord Genuity Limited (“Canaccord”) and Peel Hunt LLP (“Peel Hunt”) are acting as joint bookrunners in relation to the Placing (the “Joint Bookrunners”). The Placing is subject to the terms and conditions set out in the Appendix to this Announcement and is expected to remain open no later than 7:00 a.m. BST on the 28 August 2026, however this remains subject to change at the discretion of the Joint Bookrunners (in consultation with the Company).
Members of the public are not entitled to participate in the Placing.
Sam Moody, CEO of Rockhopper Exploration plc, said:
“This proposed Capital Raising ensures Rockhopper can participate in the acquisition of its pro-rata share of the OSX-1 and associated work in preparation for the consequential accelerated development of the central development area. We are delighted with the indications of interest from existing and potential new investors.
“I would like to remind investors that the Company is in a great position today. Not least I would highlight that we are on track for First Oil from Sea Lion in Q1 2028 with development drilling expected to commence early next year. The new NSAI report published on 26 August 2026 shows a $788m increase to our NPV10 for our 2P+2C barrels and we are planning for further exploration drilling in the basin with some material exploration prospects also re-confirmed in our latest NSAI report. I look forward to keeping shareholders updated as we deliver these catalysts.”
The Company considers it important that existing Shareholders who are not participating in the Placing are given an opportunity to acquire New Ordinary Shares at the Issue Price. The Company therefore confirms it is providing existing Shareholders with the opportunity to subscribe for New Ordinary Shares at 70 pence per New Ordinary Share pursuant to an Open Offer to raise gross proceeds of up to approximately US$20 million (c. £14.4 million) if fully taken up.
The Open Offer will include an excess application facility to enable Shareholders to apply for additional New Ordinary Shares in excess of their basic entitlements under the Open Offer. A circular setting out full details of the Open Offer (the “Circular”) is expected to be published on the Company’s website and posted to Shareholders who have elected to receive hard copies of Shareholder documentation on or around 28 August 2026.
For further details of the Open Offer, see “Summary of the Open Offer” section below.
The Placing and the Open Offer are to be effected using the authorities to allot and issue new shares granted to the Directors by Shareholders at the Company’s annual general meeting held on 30 June 2026.
Each Placee participating in the Placing who is an existing shareholder of the Company will undertake not to take up its Open Offer entitlements as a condition of its participation in the Placing.
The net proceeds of the Placing and Open Offer are expected to be used by the Company to fund the following business activities in the Falkland Islands:
-
c.US$100 million to fund Rockhopper’s estimated funding requirement for the central development area (“CDA”), as well as its estimated proportionate cost of OSX-1, to mid-2028, which is after Q1 2028, the expected point of receiving positive cash flow from NDA phase 1;
-
US$20 million to fund Rockhopper’s portion of exploration and well-deepening activities to be undertaken as part of the NDA Phase 1 development;
-
US$20 million to ensure the early project failure contingent liability provisions for NDA Phase 1 are adequately covered; and
-
US$60 million for additional contingency for all of its Falkland Islands activities, providing flexibility and funding to the targeted CDA FID in mid-2028.
The Company acknowledges that it is seeking to issue Placing Shares pursuant to the Placing amounting to approximately 22% of its existing issued Ordinary Share capital on a non-pre-emptive basis pursuant to the arrangements described in this Announcement. The Company has consulted with certain of its major institutional Shareholders ahead of the release of this Announcement. These Shareholders are supportive of the proposed structure, which has been chosen to maximise certainty of funding to ensure the Company is able to secure the equity funding it requires to fund its proportion of the OSX-1 acquisition and related costs, which the Board believes has the potential to accelerate the development of the CDA of Sea Lion and which in turn could assist in delivering significant value to all Shareholders. The Board’s unanimous view is that the Placing is in the best interests of Shareholders, and will promote the Company’s long-term success.
Capital Raising Highlights
The Placing
-
The Company intends to issue the Placing Shares by way of a non-pre-emptive cashbox placing.
-
Placees will participate through the Bookbuild which will open immediately and be subject to the terms and conditions set out in the Appendix to this Announcement.
-
The timing for the close of the Bookbuild shall be at the discretion of the Joint Bookrunners, in consultation with the Company.
-
Allocations of the Placing Shares between Placees will be determined by the Company in its absolute discretion, in consultation with the Joint Bookrunners.
-
For the avoidance of doubt, the Capital Raising is not being underwritten by the Joint Bookrunners or any other party, whether as to settlement risk or otherwise.
-
The Company will allot and issue the Placing Shares on a non-pre-emptive basis to Placees in consideration for Canaccord transferring its holdings of redeemable preference shares and ordinary shares in a Jersey special purpose vehicle (“JerseyCo”) to the Company. Accordingly, instead of receiving cash as consideration for the allotment and issue of the Placing Shares at completion of the Placing, the Company will own all of the issued ordinary shares and redeemable preference shares of JerseyCo, whose only asset will be its cash reserves, which will represent an amount approximately equal to the net proceeds of the Placing (net of any agreed commission and expenses).
-
The Placing is conditional upon, inter alia:
o the Placing Agreement becoming unconditional and not having been terminated by the Joint Bookrunners in accordance with its terms; and
o Admission becoming effective by not later than 8.00 a.m. on 2 September 2026 (or such later date as may be agreed by the Company and the Joint Bookrunners being no later than 8.00 a.m. on the Long Stop Date).
· The Placing is not conditional upon the Open Offer, but the Open Offer is conditional on the Placing.
-
The Appendix to this Announcement (which forms part of this Announcement) contains the detailed terms and conditions of the Placing.
-
The Company expects to publish a Circular in connection with the Open Offer following the closure of the Bookbuild. Full details, including terms and conditions, of the Open Offer will be included in the Circular. A subscription by Placees for Placing Shares under the Placing will not carry with it any entitlement to subscribe for new Ordinary Shares under the Open Offer.
-
At the Company’s 2026 Annual General Meeting held on 30 June 2026, the Directors were granted authorities to allot shares or rights to subscribe for or to convert any security into shares under section 551 of the Act. This authority is sufficient to enable the Company to allot and issue the total number of New Ordinary Shares to be issued pursuant to the Capital Raising.
-
Application will be made to the London Stock Exchange for the Placing Shares to be admitted to trading on AIM. It is expected that Admission in respect of the Placing Shares will become effective and that dealings in respect of the Placing Shares will commence at 8.00 a.m. on 2 September 2026.
-
As announced on 24 August 2026, the Company decided to utilise a Capital Access Window in connection with this Capital Raising. This is a voluntary pause to the trading of a Company’s shares to make it easier for companies to reach a broader range of investors during a fundraise. The Company remains in a Capital Access Window, and trading in the Ordinary Shares will remain paused, until a further announcement is made detailing the results of the Placing. The Company anticipates being able to announce the results of the Placing later today with the Capital Access Window coming to an end, and to confirm when trading in the Ordinary Shares will recommence.
The Open Offer
-
As noted above, the Company considers it important that Shareholders who were not able to take part in the Placing have an opportunity to subscribe for new Ordinary Shares at the Issue Price. The Company is therefore providing existing holders of Ordinary Shares as at 6.00 p.m. on 26 August 2026 (being the “Open Offer Record Time”) (“Qualifying Shareholders”) with the opportunity to subscribe for up to 20,529,259 Open Offer Shares at the Issue Price pursuant to the Open Offer, to raise up to approximately US$20 million (c. £14.4 million) if fully taken-up.
-
Subject to the fulfilment of certain conditions, the Open Offer will provide Qualifying Shareholders with the opportunity to apply to acquire Ordinary Shares (the “Open Offer Shares”) at the Issue Price pro rata to their holdings of Existing Ordinary Shares against all Existing Ordinary Shares held by Qualifying Shareholders as at the Open Offer Record Time on the following basis:
1 Open Offer Share for every 42 Existing Ordinary Shares held by Qualifying Shareholders
(the “Open Offer Entitlement”)
-
Entitlements to apply to acquire Open Offer Shares will be rounded down to the nearest whole number and any fractional entitlements to Open Offer Shares will be disregarded in calculating an Open Offer Entitlement and will be aggregated and made available to Qualifying Shareholders pursuant to an excess application facility.
-
The Open Offer is structured to allow Qualifying Shareholders to subscribe for Open Offer Shares at the Issue Price pro rata to their holdings of Existing Ordinary Shares against all Existing Ordinary Shares held by Qualifying Shareholders. Qualifying Shareholders may also make applications in excess of their pro rata initial entitlement up to an amount equal to the total number of Open Offer Shares available under the Open Offer less an amount equal to such Qualifying Shareholder’s Open Offer Entitlement. To the extent that pro rata entitlements to Open Offer Shares are not subscribed for by Qualifying Shareholders, such Open Offer Shares will be available to satisfy such excess applications. Applications under the excess application facility may be allocated in such manner as the Directors may determine, in their absolute discretion, and no assurance can be given that any applications under the excess application facility by Qualifying Shareholders will be met in full or in part or at all. Applications made under the excess application facility will be scaled back at the Directors’ discretion if applications are received from Qualifying Shareholders for more than the number of Open Offer Shares available under the excess application facility.
-
The Circular containing further details of the Open Offer, together with an Open Offer Application Form for Qualifying Shareholders who hold their Ordinary Shares in certificated form, is expected to be posted to Shareholders on 28 August 2026.
-
Details of the expected timeline for the Capital Raising, including the Open Offer timeline are included in the “IMPORTANT INFORMATION” section below.
Current Trading and Prospects
The Company’s results for the twelve months ended 31 December 2025 were released on 3 June 2026. A copy of these results can be found at www.rockhopperexploration.co.uk
.
As noted in the Company’s results for the twelve months ended 31 December 2025, as at 31 December 2025, the Group had (audited) cash resources of approximately US$171 million. Save as set out below, there have been no material changes to the performance of the Group since the publication of these results.
Recent Events
Northern Development Area Phase 1
On 10 December 2025, the Northern Development Area (“NDA”) Phase 1 (“NDA Phase 1”) of the Sea Lion Project was sanctioned, with both Rockhopper and its partner and operator, Navitas PDP, making their final investment decision (“FID”) to proceed with the Project.
The project financing for the NDA Phase 1 consisted of US$1.0 billion of senior debt (of which US$350 million is debt attributable to Rockhopper) with the balance being provided via a combination of joint venture equity and post first oil cash flows. Rockhopper benefits from previously disclosed financing loans from Navitas PDP in relation to the NDA Phase 1 and as a result, the initial net Rockhopper equity requirement was confirmed at US$102 million. Rockhopper financed this through an equity raise in 2025. The Aoka Mizu, being the FPSO being selected for NDA Phase 1 development, was diverted from a Middle Eastern to an Asian shipyard for refurbishment to mitigate risks from the ongoing security situation arising from the Iran conflict, this increased the net Rockhopper equity requirement to $107 million.
Notwithstanding the Aoka Mizu’s diversion the development timeline of NDA Phase 1 has remained as initially scheduled with ground works in the Falkland Islands progressing as planned and procurement of long lead items continuing. The development drilling for the NDA Phase 1 is expected to commence in early 2027 with first oil on target for Q1 2028.
As a result of taking FID on NDA Phase 1 development, in April 2026, Rockhopper was able to publish an updated independent reserves and resources evaluation by NSAI (the “April 2026 NSAI Report”), whereby volumes previously classified as contingent resources were reclassified into reserves.
The April 2026 NSAI Report confirmed:
-
110 million barrels (2P reserves) net to Rockhopper.
-
211 million barrels (2C resources) net to Rockhopper.
-
An estimated NPV10 of approximately US$966 million attributable to Rockhopper’s share of 2P reserves and NPV10 of approximately US$1,202 million attributable to Rockhopper’s share of 2C resource (in aggregate 2P + 2C of US$2.2 billion)*.
* using long-term Brent crude oil price of US$73.63/bbls
Acceleration of Central Development Area (“CDA”)
In May this year Navitas confirmed it was investigating accelerating the development of subsequent phases of the Sea Lion development beyond NDA Phase 1. Accordingly, Navitas (via a subsidiary) signed a memorandum of understanding to secure an additional FPSO. Navitas estimated this could increase the Sea Lion production capacity by a further 125,000 bopd (43,750 bopd net to Rockhopper) and accelerate subsequent production phases when compared to pre-existing plans.
On 24 August 2026, Navitas announced that one of its subsidiaries had exercised an option to acquire OSX-1, and that completion of this acquisition is expected to occur in September 2026. The aggregate gross cost of acquiring OSX-1 (excluding the anticipated upgrade costs) is approximately US$125 million. Navitas (via its subsidiary) will initially be the sole owner of OSX-1 through an incorporated special purpose vehicle and will bear 100% of the related costs until Rockhopper funds its proportionate share of the acquisition costs of OSX-1.
Navitas intends for OSX-1 to be used to develop the resources in the CDA of the Sea Lion field, thereby accelerating production of these barrels. The CDA is expected to include the drilling of 20 wells in CDA Phase 1 and 18 wells in CDA Phase 2, for a total of 38 wells. Navitas intends to submit the CDA Development Plan to FIG for approval in 2027 and to make a FID in respect thereof in the first half of 2028. Navitas is targeting production from the development of CDA Phase 1 by the end of 2030.
Rockhopper Updated Independent Reserves and Resources Evaluation
On 26 August 2026 Rockhopper announced the publication of a further updated NSAI Report which incorporates the accelerated development plan for the CDA following the purchase of OSX-1 (the “August 2026 NSAI Report”).
The August 2026 NSAI Report shows:
-
Reconfirmation of 2P Reserves of 110 million barrels net to Rockhopper.
-
an NPV10 attributable to Rockhopper’s share of 2P + 2C resources of US$2.9 billion* representing a 36.4% increase when compared to the previous April 2026 NSAI Report.
-
2C development pending resources of 162 million barrels net to Rockhopper representing an approximate 12% increase when compared to the previous April 2026 NSAI Report. Total 2C resource net to Rockhopper of 219 million barrels.
* using long-term Brent crude oil price of US$75.95/bbls
The full August 2026 NSAI Report is available on Rockhopper’s website.
Background to and reasons for the Placing
Acceleration of Sea Lion development
The Directors believe that there is significant value to the Company and its partner Navitas, in accelerating the later phase of the Sea Lion development, as supported by the August 2026 NSAI Report published yesterday. In this regard, as stated above, Navitas (via a subsidiary) has recently exercised its option to purchase OSX-1 to be utilised in the development of the CDA phase and has commenced work towards targeting a possible FID in 2028.
Although the acquisition of OSX-1 falls outside the scope of the existing joint venture arrangements between Navitas PDP and Rockhopper, discussions between the parties regarding the optimal structure for the acquisition of OSX-1 remain ongoing. Therefore, in order to be in a position to take up its pro rata interest in OSX-1 (35%) and to fund any associated pre-FID costs for the CDA, the Company is undertaking the Placing.
Navitas has indicated that capital expenditure associated with OSX-1 and related activities is expected to total approximately US$190 million through to the end of 2027. Rockhopper estimates that US$100 million is sufficient to fund its CDA requirements to mid 2028, by which time it expects to be receiving positive cash flow from NDA Phase 1.
Accretive Exploration and Balance Sheet Strength
Having considered several factors, including current market conditions, the Directors believe it is the correct time to seek additional liquidity to support other potential value-enhancing activity and otherwise strengthen the Company’s balance sheet.
In particular, Navitas is considering various options for exploration activity during the drilling campaign for NDA Phase 1 which may include an oil exploration well in the licence covering the Sea Lion discovery area and the deepening of a development well to target the Gwendoline exploration prospect (Gross 2U 53.2 mmbbls of prospective resource). A portion of the proceeds of the Placing will used by Rockhopper to ensure it has the requisite liquidity to meet its proportion (currently 35%) of the costs associated with these activities in the Falkland Islands.
As regards balance sheet strength, on NDA Phase 1 of the Sea Lion development, Navitas PDP and Rockhopper have to cover the contingent early project failure decommissioning funding requirement, which FIG requires to be secured and funded as the Project is developed in the unlikely event of early project failure pre-production. As previously announced this early project failure requirement is currently estimated at US$52.5 million net to Rockhopper. Rockhopper has investigated the possibility of covering this via a combination of surety bond, parent company guarantees, cash and/or any other suitable instrument. Currently, Rockhopper has not secured a suitable surety bond. Rockhopper currently holds US$35 million in cash allocated to cover its US$52.5million exposure and an additional US$20 million would enable Rockhopper to provide a suitable instrument which will be returned to Rockhopper (less costs) as the end-of-life decommissioning fund builds up post first oil on the NDA Phase 1.
The Directors are aware that the Sea Lion Project, with its multiple development phases and material exploration upside elsewhere in the licence, represents significant value to the Company’s shareholders. However, the Directors are also aware that offshore developments in remote locations are very capital intensive. It is therefore vital for Rockhopper, as a pre-revenue company, to be as well capitalised as possible to build in contingencies and to have the flexibility to respond to opportunities as they arise.
Listing Venue Update
Following completion of the Capital Raising, Rockhopper intends to evaluate a potential transfer of its listing to the Main Market of the London Stock Exchange and, in parallel, assess a potential dual listing on the Tel Aviv Stock Exchange. Further updates will be provided in due course.
Use of Proceeds
The Company expects the Capital Raising to qualify as “Permitted Equity Funding” under the terms of the co-venturers’ loan agreement. The net proceeds of the Placing and Open Offer are expected to be used by the Company to fund the following business activities in the Falkland Islands:
-
c.US$100 million to fund Rockhopper’s estimated funding requirement for the CDA, as well as its estimated proportionate cost of OSX-1, to mid-2028, which is after Q1 2028, the expected point of receiving positive cash flow from NDA phase 1;
-
US$20 million to fund Rockhopper’s portion of exploration and well-deepening activities to be undertaken as part of the NDA Phase 1 development;
-
US$20 million to ensure the early project failure contingent liability provisions for NDA Phase 1 are adequately covered; and
-
US$60 million for additional contingency for all of its Falkland Islands activities, providing flexibility and funding to the targeted CDA FID in mid-2028.
Risk Factors
Please see pages 16 to 25 of the Company’s 2025 Annual Report and Accounts issued on 5 June 2026 for a list of principal risks and uncertainties facing the Company which include, inter alia, potential requirements for additional capital in connection with cost overruns, project delays or debt facility disruption, disputes in respect of the sovereignty of the Falkland Islands, joint venture alignment and non-operator status, , oil price uncertainty and health, safety, environment and security risks. Any investment in the New Ordinary Shares is subject to a number of risks and uncertainties. The risk factors described in the 2025 Annual Report and Accounts and those set out below do not purport to be a complete list or explanation of all the risks involved in investing in the New Ordinary Shares, or that may adversely affect the Company or its business.
Please see below certain key risk factors related to the business of the Group.
1. The Company has limited control over the process for acquiring OSX-1
The OSX-1 acquisition is being pursued at Navitas’s initiative. As Rockhopper does not have control over Navitas’s acquisition of OSX-1, nor is it the operator of the relevant licences, there can be no assurance that such plans will not be modified, delayed or abandoned. Navitas (via a subsidiary) has exercised its option to acquire OSX-1 and completion of the acquisition is expected in September 2026. However, Rockhopper is not party to the acquisition arrangements, as expected for a non-operated partner has not been involved in the due diligence process and, given the purchase is being conducted by Navitas solely, has had no ability to influence the terms agreed between Navitas and the selling counterparty. Accordingly, Rockhopper has limited visibility over the terms negotiated by Navitas, and will, through its acquisition of its pro rata share of the SPV (should ownership terms be agreed), be bound by the terms negotiated by Navitas with the selling counterparty.
In addition, although OSX-1 is expected to be suitable for deployment on the CDA Sea Lion development, its specifications and operational performance may ultimately differ from what is currently envisaged by Navitas and there can be no assurance that OSX-1 will perform in line with current expectations.
2. Even if OSX-1 is successfully acquired and the Company acquires its pro rata interest, there is no guarantee that this will accelerate subsequent development phases of Sea Lion and further funding will still be required
First Oil on NDA Phase 1 of the Sea Lion development remains on track for Q1 2028. Although the acquisition of OSX-1 is an important step in accelerating progression of the CDA towards FID, its acquisition alone will not be sufficient to achieve FID and a number of other conditions must be satisfied. Accordingly, whilst the acquisition of OSX-1 and other long lead items is intended to accelerate the progression of the CDA towards FID and, consequently, further phases of the Sea Lion development, there can be no certainty that this objective will be achieved.
In addition, as for any project of this type and scale, it is possible that the aggregate costs associated with the acquisition of OSX-1 and the broader development of the CDA may exceed current expectations due to unforeseen technical, logistical or other circumstances.
The Directors believe, taking into consideration the proceeds of the Placing and Navitas PDP’s current cost estimates as operator, that the Company will have sufficient funds to meet its proportion of costs through to FID for the CDA which is targeted around the middle of 2028, post First Oil at NDA Phase 1 which is currently on track to take place in Q1 2028. The CDA is a large-scale development. At this stage, Navitas PDP estimates that the development budget for CDA is expected to be approximately US$ 3 billion, of which approximately US$ 1.15 billion is attributable to the acquisition, upgrade and adaptation of the OSX-1. During the coming year, Navitas PDP will examine various alternatives for financing the upgrade of the OSX-1. Further funding will be required, over and above the proceeds of the Placing, to fund the Company’s proportion of costs to enable FID for the CDA to take place. There is no assurance that such funding will be available on acceptable terms, or at all. In addition, if FID for the CDA is delayed materially beyond the middle of 2028, there is no assurance that the proceeds of the Placing will remain sufficient to fund the Company’s proportion of pre-FID costs, and the Company may require additional funding earlier than currently anticipated. Furthermore, the current cost estimates and economics of the CDA are based on the project’s present stage of definition, and further engineering, subsurface and commercial work remains to be completed before FID. Accordingly, there can be no assurance that the estimated costs, specifications, performance or economics of the CDA will not change, potentially materially, as that work progresses. Any such change, or any delay in the anticipated timing of FID for the CDA, could have a material adverse effect on the Company’s financial position, results of operations and/or prospects.
3. No legally binding arrangements are currently in place for the Company to acquire legal ownership of its pro rata interest of the vehicle purchasing OSX-1
As a 35% non-operating partner in the Sea Lion development, Rockhopper does not exercise day-to-day control over development decisions, which are directed by Navitas in its capacity as operator. In that capacity, Navitas has been evaluating the acceleration of the Sea Lion development beyond NDA Phase 1, by the proposed development of the CDA. In order to provide optionality for the development of the CDA, Navitas (via a subsidiary) is pursuing the acquisition of OSX-1 and will initially be the sole owner of OSX-1 (through an incorporated special purpose vehicle) (“SPV”), until such time as Navitas and Rockhopper agree terms in respect of the ownership of the SPV.
Based on the discussions with Navitas to date, Rockhopper is confident that a suitable agreement will be reached. If terms are agreed, Rockhopper will need to contribute its proportionate share of the OSX-1 acquisition and related costs to the SPV within an agreed period of time. However, there can be no guarantee that Navitas and Rockhopper will agree commercially viable terms in respect of the ownership of the SPV or that Navitas will transfer a proportionate share of ownership of the SPV to Rockhopper.
If terms are not agreed, the Company will still have the ability to participate in the broader Sea Lion development (including development of the CDA) through its 35% interest under terms contained within the relevant joint operating agreements. Any use of OSX-1 in connection with Sea Lion development would need to be approved through the relevant joint operating agreements. In addition, Rockhopper believes it is in both parties’ interest for SPV ownership to be structured in a mutually agreeable form and expects that this will be achieved.
4. First Oil may not occur or may be materially delayed
Based on current development plans, the Company’s base case assumption is that it will have sufficient financial resources to reach First Oil NDA Phase 1. However, as with all projects of this nature, various factors, certain of which may not be within the Company’s control, could result in First Oil not being achieved or being materially delayed. These include, amongst other things, unforeseen operational delays that could render the existing project financing package insufficient to reach First Oil. Whilst the Company is not the operator and the project is currently on track (with no indication at present that First Oil will be delayed), any such adverse developments could have a material adverse effect on the Company’s financial position, results of operations and/or prospects. Whilst the Company does not anticipate an overspend relative to the approved budget, in those circumstances, the Company may need to secure additional financial resources in order to reach First Oil.
5. Expiry of key licence interests in the North Falkland Basin
As noted in the 2025 Annual Report and Accounts, other than the licences for NDA Phase 1 and Phase 2, all other licences outside the Sea Lion approved development area, including the licences immediately to the south of the Phase 1 development area (which incorporate resources forming part of the CDA) are due to expire on 31 December 2026.
Discussions with FIG in respect of extensions to these licences are being conducted separately by the relevant licence operators. Navitas PDP, as operator, is leading all discussions with FIG in respect of extensions to the licences in which the Company holds a joint interest with them.
Consistent with historic practice, extensions to these licences are currently expected to be granted. However, no guarantee can be given that any or all of these extensions will be received. Whilst not expected, should any of the relevant licences expire without extension, the Company would not be able to produce the resources attributable to the licence areas affected, which may have a material adverse effect on the Group’s business, financial condition, and/or results of operations.
Rockhopper’s Other Falkland Licence Interests
In addition to the licences in the North Falkland Basin, the Company holds a 100 per cent. interest and is the operator of licences PL011, PL012 and PL014 in the South and East of the Falkland Islands.
The Company considers these licences to be potentially prospective for gas resources. In particular, licence PL011 is adjacent to a large gas-condensate discovery made by Borders & Southern Limited in April 2012.
These licences are due to expire on the 31 December 2026. Discussions in respect of these licences are being handled by Rockhopper. As noted above, consistent with historic practice, extensions to these licences are currently expected to be granted. However, no guarantee can be given that any or all of these extensions will be received.
All amounts in this Announcement are based on an exchange rate of £1:US$1.35903, being Bloomberg’s exchange rate as at 16:30 BST on 26 August 2027.
Enquiries:
Rockhopper Exploration plc
Sam Moody – Chief Executive Officer
Tel. +44 (0)20 7390 0230 (via Vigo Consulting)
Canaccord Genuity Limited (Joint Bookrunner, NOMAD and Joint Broker)
Henry Fitzgerald-O’Connor/James Asensio/Charlie Hammond (Investment Banking)
Sam Lucas/Darren Furby (ECM)
Tel. +44 (0) 20 7523 8000
Peel Hunt LLP (Joint Bookrunner and Joint Broker)
Richard Crichton/Georgia Langoulant
Sohail Akbar/Ambika Bose
Tel. +44 (0) 20 7418 8900
Vigo Consulting
Patrick d’Ancona/Ben Simons/Fiona Hetherington
Tel. +44 (0) 20 7390 0234
Share this story - choose your platform:
Facebook
X
Reddit
LinkedIn
Tumblr
Pinterest
Vk
Email
RNS announcements
A complete archive of our RNS announcements can be found in Investors
News archive
News archive Select Month October 2026 September 2026 August 2026 June 2026 May 2026 April 2026 January 2026 December 2025 September 2025 August 2025 July 2025 June 2025 May 2025 March 2025 January 2025 November 2024 October 2024 September 2024 June 2024 May 2024 January 2024 December 2023 September 2023 August 2023 July 2023 May 2023 April 2023 March 2023 November 2022 October 2022 September 2022 August 2022 July 2022 June 2022 May 2022 April 2022 February 2022 December 2021 September 2021 June 2021 May 2021 March 2021 December 2020 November 2020 September 2020 August 2020 June 2020 May 2020 April 2020 March 2020 February 2020 January 2020 December 2019 November 2019 October 2019 September 2019 August 2019 July 2019 June 2019 May 2019 April 2019 February 2019 January 2019 November 2018 September 2018 July 2018 June 2018 May 2018 April 2018 February 2018 January 2018 September 2017 August 2017 June 2017 April 2017 March 2017 February 2017 December 2016 September 2016 August 2016 May 2016 April 2016 February 2016 January 2016
Page load link
Go to Top