UK Power Transmission & Distribution: Investor Day 15 October 2026 Image: Skye 132kV Reinforcement Project, Scotland Philip Hoare Group Chief Executive Image: Kinardochy Substation 400kV overhead line, UK Strong and diversified Group Across…
UK Power Transmission
& Distribution:
Investor Day
15 October 2026
Image: Skye 132kV Reinforcement Project, Scotland
Philip Hoare
Group Chief Executive
Image: Kinardochy Substation 400kV overhead line, UK
Strong and diversified Group
Across
geographies by revenue
Core our
geographies
UK 48%
InGrowth
our growth
markets
markets
Profitable growth framework
UK Energy
UK Defence
US 52%
End-to-end
capability
UK Transport
US Buildings
Design &
Engineering
£21 billion high-quality & diversified order book
Programme
Management
Construction
Management
Construction
Project Finance
£1.1 billion Investments portfolio
Operations &
Maintenance
Profitable growth framework: long-term value creation
Evolve
Strengthen
the core
Improve
margins
Drive
operational
excellence
Shape our
portfolio
Advance
our people
strategy
Invest in
what
matters
Long-term value creation
Zero Harm
Energise
Accelerate
profitable
growth
Deepen
customer
relationships
Explore
Shape
what’s next
Accelerate
profitable
US growth
Accelerate
profitable
growth
in key UK
markets
Sustainable
Customer focused
Employer of choice
Explore
adjacencies
and
innovation
Profitable growth
UK Power Transmission: growth accelerating
Strong momentum following three years of growth
Target market: 2025-30
Source: Internal estimates
UK power transmission market
Power revenue: 2025
£366 million
H1 revenue
£2.1 billion
order book
130% increase vs
H1 2023
Five-fold increase
vs H1 2023
£6-8 billion
of further
pipeline
awarded
Design & engineering
Specialist plant
Project management
Construction delivery
Manufacturing
Commissioning
Largest workforce
and end-to-end
capabilities
2025
2026
25%
2027
2028
2029
estimated 2025
market share
2030
Nick Crossfield
Divisional CEO: UK Defence,
Power & Regional Infrastructure
Image: Tealing Substation, Dundee
Balfour Beatty delivers across all of the onshore grid
Balfour Beatty market
Offshore wind & interconnectors
(HVDC)
Transmission network 275kV
and above (HVAC)
Distribution network
132kV and below (HVAC)
3
4
5
7
HVDC
onshore
cabling
Transmission
substations
Transmission
overhead lines
Yes
Yes
Yes
2
3
Key
Asset class
1
2
HVDC
Offshore
converter
cabling
stations
Capability held No
Yes
6
8
9
Transmission Distribution
cabling
substations
Distribution
overhead
lines
Distribution
cabling
Yes
132kV only
Yes
132kV only
Structural demand is driving sustained market growth
The UK electricity network must expand at an unprecedented pace to meet the demands that are being
placed on it
Government priorities
Long-term structural drivers
Net Zero 2050
Electrification
Clean Power 2030
Generation changes
Energy security
Data centres
Cost of living
Aging assets
The largest
expansion
of the UK
grid in over
70 years
The transmission investment is clearly set out until 2031
c.£80bn of investment to 2031 provides strong platform for growth, with further plans beyond 2030
o
Plans to upgrade 3,500km of
overhead lines and build 25 new
substations
o
Growing workforce by c50%
o
£35bn investment programme
spanning 2026-2031
Example projects
BTNO, Woolavington, Eastern
Green Link 2 Cabling
o
Developing network for 20%
of UK clean power demand
o
Support 37,000 jobs
o
£29bn investment programme
spanning
2026-2031
Example projects
Beauly-Peterhead, Longside,
Argyll, Skye
o
Plans to build 12 substations
and upgrade 450km of overhead
lines
o
1,400 new direct jobs created
and 11,000 jobs in supply chain
o
Up to £12bn investment
programme from 2026-31
Example projects
Windyhill-Denny North
The distribution opportunity
Distribution represents a further growth opportunity for Balfour Beatty, as client investment is expected to
accelerate. Growth will be targeted based upon our value offering
Balfour Beatty has a 10% market share in distribution¹
£50bn of investment forecast to 2050, at least double current
annual levels²
Investment will accelerate most steeply in next 5-10 years,
driven by local generation and electrification
This increased demand will likely result in more multi-stage
contracts and long-term, strategic partnerships in RIIO-ED3
(2028-2033)
Our target market is large, complex programmes where Balfour
Beatty’s end-to-end capabilities and scale adds most value
¹ Internal estimates
² National Infrastructure Commission, Electricity distribution networks: Creating capacity for the future (February 2025)
Beyond 2030, the market outlook remains very strong
Capacity constraints and demand increases will continue to be prevalent in the medium to long-term,
driving further grid investment
Without investment, the cost of
insufficient grid capacity¹ will
treble between 2031 and 2035
Electricity demand will
accelerate and more
than double by 2050
“Beyond 0 0” report reconfirms investment need:
£89bn already identified post-2030, compared to £64bn pre-2030²
43 major transmission projects already identified at a value of £33bn
In areas where Balfour Beatty has a strong presence
Half require early investment and delivery by the mid-2030s
¹ Being curtailment charges to switch off generation and balancing costs to maintain grid stability
² National Energy System Operator (NESO) “Beyond 2030 – Electricity Transmission Update” (June 2026)
Map of recommended Beyond
2030 network (NESO)
Iain Smith
New Business & Strategy Director
Power Transmission & Distribution
Tony Wilson
Managing Director
Power Transmission & Distribution
Image: London Power Tunnels
How power transmission and distribution is funded
o
Government policy and demand outlook set wider
context
o
NESO identifies whole-system network requirements
o
Balfour Beatty’s clients, the network owners, develop
investment plans
o
OFGEM approve investment as value for money
o
The network owners finance and build the infrastructure
o
Regulated returns are recovered through electricity bills
o
This investment is not funded through the treasury
Investing in the grid is the sustainable route to lower energy bills
Significant funding underpins market growth
The regulatory mechanisms are already in place to fund investment and accelerate priority projects
RIIO
(Revenue = Incentives + Innovation + Outputs)
ASTI
(Accelerated Strategic Transmission Investment)
• RIIO are the regulatory investment periods for the
network owners
• Introduced in 2022 for major transmission schemes
• Established since 2013, it balances investment
certainty with consumer value
• RIIO-T3, for transmission, is from 2026-31
• Earlier funding supports development, design and
procurement
• OFGEM continue to scrutinise cost and
consumer value
• RIIO-ED3, for distribution, will be from 2028-33
RIIO is well-established and supports
investment certainty
ASTI has enabled earlier investment to help
speed up infrastructure build
Leading framework positions provide access to growth
We have secured routes into the principal customer programmes and different asset classes, through which
most of this capital investment is being procured
Client
Region
Framework position
Value¹
England
& Wales
Electricity Transmission Partnerships
HVDC Civil Framework
RIIO Frameworks
Distribution Frameworks
£9bn
£12bn
Not disclosed
Not disclosed
North
Scotland
Pathway to 2030 Framework (ASTI)
£10bn
RIIO Frameworks
Not disclosed
South
Scotland
Strategic Overhead Line
Agreement
£3bn
Underground cables
Substations
Overhead lines
Asset types
Converter stations
¹ Client’s full published value for framework, where available. Where unavailable, these are combinations of long-standing frameworks without published values.
Multi-stage contracting creates greater project certainty
Former approach:
Traditional Design & Build model
Current approach:
Multi-stage
contract model
Single Design & Build (D&B) contract
Detailed design
and procurement
Initial design
Part A / first phase
Benefits of early involvement
Surveys
Consents
Design
Value
engineering
Construction
Part B / second phase
Improved project certainty
Procurement
Cost
certainty
Schedule
certainty
Cost
efficiency
Our position is supported by a set of clear differentiators
We operate in the complex, specialist and large-scale part of the market, where barriers to entry are high
and the capabilities of Balfour Beatty offer the most value
Barriers to entry
Balfour Beatty differentiators
o
Safety critical industry,
accreditations needed
o
100-year track record of delivering
complex, major power projects
o
Highly regulated clients
with strict specifications
o
o
Long-term frameworks
End-to-end offering, deploying
specialist capabilities across the
project lifecycle
o
Specialist knowledge
and capabilities
o
The largest design and delivery
workforce, deployed nationwide
o
Scale and breadth
o
Leading the industry in investment
in capacity and innovation
We are proven in delivering major, complex power projects
Balfour Beatty has been involved in most major transmission upgrades in the last 20 years, and is now
delivering the next phase of the UK’s most significant power projects
Completed schemes
In delivery
Mobilisations
Peterhead
Netherton Hub
Beauly-Peterhead
SSE’s first 400kV
substation
Green energy hub that is
bigger than Monaco
The largest overhead line
project in the UK
Viking Link
Woolavington
Skye
The longest interconnector
in the world
Connecting the UK’s
largest EV battery factory
Securing power for Skye
& the Western Isles
Hinkley Connection
Argyll
Birkhill Wood
World first “T Pylon”
structures
Major electricity upgrade for
Argyll & Bute
Connecting 3 offshore wind farms
to power 4 million homes
Overhead lines
Underground cables
Substations
Converter stations
We have end-to-end capability from design to energisation
Balfour Beatty can integrate delivery and deploy multiple specialist capabilities on power projects
Design &
engineering
Project
management
Manufacturing
Specialist plant
Construction
delivery
Spotlight:
design & engineering
Spotlight:
specialist plant
Spotlight:
construction delivery
•
•
•
•
•
•
550 designers in UK and India
Integrated design and
construction is a
Balfour Beatty differentiator
4D and digital tools
Supported by Strategic
Design Partners
•
Largest specialist
transmission plant
holding in the industry
Significant investment
in upgrading
equipment in
readiness for growth
•
Commissioning
Ground engineering
capability delivers piling and
ground works for overhead
lines and substations
Investing in design, plant and
innovation to support growth
in Power works
Spotlight: Manufacturing – Painter Brothers
Balfour Beatty is the only contractor with in-house manufacturing of steel towers and substation structures,
meaning we can offer vertical delivery, whilst also supplying structures into the wider market
Overview
52,000m2
Hereford
manufacturing
facility
1 of 3
major suppliers
in the UK
industry
1,500
towers being
supplied for
Balfour Beatty
5,000t
10,000t
15,000t
2023 capacity
per year
current capacity
per year
planned capacity
per year
Painter Brothers supports the integrated, vertical delivery
of power projects
In-house capability
In-house precision steel fabrication
strengthens Balfour Beatty’s end-to-end
infrastructure proposition
Vertical offering
Our unique vertical offering reduces
interfaces and supports efficient delivery
Wider market
It’s specialist capability means it is also
supplying the wider market with towers and
structures
We deploy the largest workforce in the UK
We have made significant strides in growing our people base, supported by a nationwide specialist supply
chain and our dedicated training schools
Largest T&D workforce
in the industry
Recruiting and
developing at pace
Nationwide
presence
Beauly-Peterhead
Skye
o
550 design and
engineering
o
900 construction delivery
o
300 project and
construction management
o
o
750 specialist project
support staff
Underpinned by our
long-term, strategic
supply chain
o
o
o
2024 – 562 experienced
hires and 71 early
careers
Emmock-Hurlie
Argyll
Motherwell
2025 – 642 experienced
hires and 94 early
careers
2026 – 700 experienced
hires and 94 early
careers
Netherton Hub
Aberdeen
Inverness
Newcastle
EGL2
Leeds
Birkhill Wood
Derby
Balfour Beatty
office/training
centre
Notable live
project
Cardiff
Woolavington
LPT2
Dartford
BTNO
Wallend
We are investing in growth and innovation
Project workforce
(direct & supply chain)
Attract
o
o
2030
c6,000
o
o
Industry attraction campaign
Record inter-company transfers
Record early careers
Utilising adjacent industries
Develop
o
2026
c3,200
2024
c1,500
o
o
o
Industry leading OHL training school
17 bespoke development pathways
Incubator programmes
Further plans to expand facilities
Retain
o
o
Improving site working environments
Developing our employee value
offering
Innovate
o
o
o
Utilising AI for productivity improvements
Implementing technology solutions such
as drones and robotics
Design and methodology standardisation
Strong position, proven capability and disciplined delivery
This market offers an excellent long-term growth opportunity for Balfour Beatty
Exceptional
market growth:
20% CAGR
Unrivalled
market
position
Unique
integrated
capability
Investment
in the
future
Significant
value
creation
Investment need is
clear up to and
beyond 2030
Balfour Beatty has
a market leading
position and
track record, with
long-term customer
relationships and
framework positions
Our combination of
end-to-end capability
in a specialist market,
supported by our
major programme
experience, is difficult
to replicate
We are actively
investing in people,
supply chain and
productivity to support
safe and effective
delivery at scale
We are focused
on better outcomes
for customers,
consumers and
shareholders as we
build a grid fit for
the future