Grange Resources Limited is an integrated iron ore mining and pellet production company. The business operates the Savage River magnetite iron ore mine in Tasmania, which has been in production since 1965, and the Port Latta pellet plant and port facility, which produces premium quality iron ore pellets. The company also owns the Southdown magnetite development project in Western Australia, an advanced project with significant mineral resources intended to supply magnetite concentrate. Grange Resources serves customers throughout the Asia Pacific region and beyond through a combination of spot and term contracted sales arrangements for its steel-making raw materials.

Summarised from the company's own disclosures, fiscal year ended Dec 2025

Industry Materials Homepage grangeresources.com.au
Sector Basic Materials IR page grangeresources.com.au/investors
Tags
magnetite mining, iron ore pellets, magnetite concentrate, steel-making raw materials, integrated mining, pellet production, Savage River, Port Latta, Southdown
Press page grangeresources.com.au/announcements

Metrics

Valuation  
Market cap $ 115.734M
Market cap (USD) $ 115.734M
P/E —
PEG —
P/BV —
P/S —
P/OCF —
P/FCF —
Dividend yield —
Turnover / mcap —
Returns  
ROE 4.3%
ROI 4.2%
ROIC 4.2%
Profit margin 9.8%
Growth  
Revenue growing No
Profits growing No
Revenue up 3y No
Revenue up 5y No
Earnings growth 3y (net profit CAGR) -35.3%
Quality  
Profitable Yes
Margin expanding No
Buying back stock No
Diluting (TTM) No
Debt/Equity —
Podcast bulls (TTM) Sign up
Podcast bears (TTM) Sign up
Podcast sentiment (TTM) Sign up
Podcast sentiment % (TTM) Sign up
News sentiment (TTM) 9
Quality score 0%
Insiders  
Buys, 1w Sign up
Buys, 1m Sign up
Buys, 1y Sign up
Sells, 1w Sign up
Sells, 1m Sign up
Sells, 1y Sign up

Sign up to see this company's insider trades

Figure FY 2025 FY 2024 FY 2023 FY 2022 FY 2021 FY 2020 FY 2019 FY 2018 FY 2017 FY 2016 FY 2015 FY 2014 FY 2013 FY 2012 FY 2011 FY 2010
Revenue 477.854M 520.805M 614.744M 594.555M 781.662M 526.324M 368.601M 368.204M 247.877M 276.345M — — 281.072M 331.308M 410.432M 229.066M
Net profit 46.6M 58.549M 150.104M 171.735M 321.615M 203.186M 77.334M 112.938M 60.713M 92.903M -277.814M -110.164M 21.83M 59.08M 216.567M 42.228M

Sign up to see institutional holdings

Sign Up

Podcast Mentions

Sign up to see podcast mentions and sentiment

Sign Up

FID to deliver the Savage River Underground Released 14 Oct. 2026. Bull 5 Bear 0 Product/operations

Grange Resources Limited ABN 80 009 132 405 34a Alexander Street, Burnie, Tasmania 7320 PO Box 659, Burnie, Tasmania 7320 T: + 61 (3) 6430 0222 E: [email protected] W: www.grangeresources.com.au

14 October 2026

Final Investment Decision to Deliver the
Savage River Underground Project

Grange Resources Limited (ASX: GRR) (“Grange” or the “Company”) is pleased to announce that its Board of Directors has made a Final Investment Decision for the North Pit Underground Project (the “NPUG Project” or “Underground Project”) at its Savage River Iron Ore Pellet Operations in northern Tasmania (the “Savage River Operations”).

The decision to proceed with the Underground Project follows a number of recent key project optimisation studies, with the Underground Project proceeding as a Sub-Level Cave (SLC) development and operation. This development will be at a significantly lower initial capital requirement compared with the previously considered Block Cave development, while preserving optionality to progress to a Block Cave in the future.

Highlights • Grange announces a Final Investment Decision to develop the North Pit Underground Project (the “NPUG Project” or “Underground Project”) at its Savage River Iron Ore Pellet Operations in northern Tasmania. • The NPUG Project is projected to be fully funded from existing cash reserves and cashflows from the ongoing open pit operations.
• All environmental approvals for the development of the NPUG Project are in place. • Underground mining at Savage River is forecast to commence in Q1 2027. • The Underground Project extends production and pellet supply continuity to 2035, with potential to extend beyond 2040 under a future Block Cave development at Savage River (or alternative open-pit options). • Base case economics (US$90/t 62% Fe fines): project NPV of A$357 million (8.3% real, after tax) and IRR of 43%. • A staged development approach that preserves the option for a Block Cave with a decision to be made at a future date.

Page 2 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Table 1 - North Pit Underground Project Base Case Economics

Key Parameters
Mine life ~10 years Project NPV (8.3% real, after tax) A$357 million Project IRR 43% Underground capital expenditure A$287 million Sustaining capital expenditure (over project life) A$234 million Product Price (average $ / tonne) A$181 C1 cash cost (average $ / tonne) A$132 (US$90) All-in cost (average $ / tonne) A$164 (US$112) Based on a flat price of US$90/t (for 62% Fe fines) and an average exchange rate of A$1.00 = US$0.68.

Staged Underground Strategy

Since 2018, Grange has progressively evaluated underground mining beneath North Pit as the means of extending mine life at Savage River. A Prefeasibility Study, supported by an Exploration Decline, resource drilling and a bulk sample, found both Block Cave (BC) and Sub- Level Cave (SLC) mining viable. The Definitive Feasibility Study for a large BC followed in February 2024, independently reviewed by technical consultants with no fatal flaws identified.
Integration with the open pit, engineering, permitting and decline extension then progressed. An Independent Technical Expert review in 2026 confirmed the project was technically credible.
However, weaker iron ore prices, rising costs, and reduced risk appetite meant the BC could not be funded at the required scale.

In response, the Board has approved the lower-capital SLC, while preserving the option of a future Block Cave. The SLC development represents the least-cost option to transition to underground mining, reduce funding requirements and external debt, and preserve long-term value for shareholders.

The SLC delivers a strong positive return, requires materially lower upfront capital than the BC, and can be self-funded, while providing optionality to a larger operation.

Next Steps

Management will now proceed to award mining contracts and mobilise, targeting commencement of underground development in Q1 2027, while progressing studies, optimisation and funding work for future stage decisions.

As part of the transition to underground mining, the Company will continue workforce planning and its transitional plan to support its evolving operational requirements.

Page 3 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Commenting on the Final Investment Decision, Grange’s Chief Executive Officer Weidong Wang said:
“The Sub-Level Cave development is a significant step for Grange and for Savage River operations. It secures our ability to continue supplying high-quality pellets to customers well into the next decade. It also maintains our options as we build the foundation for a large-scale underground mine. This represents a significant investment in our operation and our community.”

Disclaimer

The material in this ASX release is not and does not constitute an offer, invitation, or recommendation to subscribe for, or purchase, any security in Grange Resources Limited nor does it form the basis of any contract or commitment. The Company makes no representation or warranty, express or implied, as to the accuracy, reliability or completeness of this material. The Company, its directors, employees, agents and consultants, shall have no liability, including liability to any person by reason of negligence or negligent misstatement, for any statements, opinions, information or matters, express or implied, arising out of, contained in or derived from, or for any omissions from this material except liability under statute that cannot be excluded.

Statements contained in this material, particularly those regarding possible or assumed future performance, costs, dividends, production levels or rates, prices, resources, reserves or potential growth of the Company or, industry growth or other trend projections are, or may be, forward looking statements. Such statements relate to future events and expectations and, as such, involve known and unknown risks and uncertainties. Actual results and developments may differ materially from those expressed or implied by these forward-looking statements depending on a variety of factors.

The Definitive Feasibility Study referred to in this ASX release has been undertaken for the purpose of evaluating the technical and economic aspects of the potential development of an underground mine at Savage River in Tasmania. The DFS has been completed to a level of accuracy of +/- 15%.

The information in this announcement that relates to Mineral Resources and Ore Reserves is extracted from the Company’s announcement titled “Savage River Mineral Resources and Ore Reserves Update” released on 2 April 2026, available at www.asx.com.au. The Company confirms that it is not aware of any new information or data that materially affects the information included in that announcement. It also confirms that all material assumptions and technical parameters underpinning the Ore Reserve estimates in that announcement continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person’s, Mr Ben Maynard, findings are presented have not been materially modified from the original announcement.

The SLC production target has been derived from an updated mine design and schedule wholly within the footprint of the existing Probable Ore Reserve. Mr Ben Maynard has reviewed the SLC design and is satisfied that it does not materially change the estimate, the modifying factors, or the economic viability of the Ore Reserve reported on 2 April 2026.

Mineral Resources converted to Ore Reserves are classified as Measured and Indicated, and no Inferred Mineral Resources are included in the production schedule. For full disclosure of Mineral Resources and Ore Reserves please see JORC Statement dated 2 April 2026.

Given the uncertainties involved, investors should not make any investment decisions based solely on the results of this study.

Page 4 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Project Background

The North Pit operations at Savage River are approaching the economic limit of open pit mining at approximately 450 metres depth. Since 2018, Grange has progressively evaluated underground mining beneath the North Pit as the means of extending mine life at Savage River. • Concept study (2018): identified Block Cave (BC) and Sub-Level Cave (SLC) mining as viable alternatives to further deepening the pit. • Prefeasibility Study (2019–2021): supported by a two-kilometre Exploration Decline, 11,000 metres of resource drilling and a bulk sample drive through the ore. Together these confirmed ground conditions, water inflows, development rates and processing performance. The Prefeasibility Study found both methods technically and economically viable, with the BC delivering the higher long-term return. • Definitive Feasibility Study (2022–2024) (DFS): further drilling, totalling 55 holes and 36,732 metres, underpinned a DFS for a large BC with inclined conveying, supported by a smaller SLC transition mine. The DFS was released to the market on 28 February 2024. An independent review found no fatal technical or economic flaws. • Integration and execution planning: the DFS was then integrated with open pit operations to remove duplicated costs, reduce stockpiles and working capital, and defer and spread capital expenditure. Engineering, permitting and decline extension progressed in parallel.
• Work completed: All permits and approvals were secured, engineering design was progressed, the Exploration Decline was extended, the performance of the underground development was observed, and the FEED study commenced. Provision was also made through state legislation to enable the early renewal of the mining lease for the next 20 years.
• Funding (2026): an Independent Technical Expert review completed as part of project financing confirmed the project is technically credible (ASX, 13 May 2026). However, lower iron ore prices, sustained cost increases, higher interest rates and slower decarbonisation timelines materially reduced risk appetite. The Company’s major shareholder indicated it would not provide financial support to the project at this stage.

In response, the Company reviewed alternative development pathways with three objectives: • reduce the upfront funding requirement and capital intensity; • maintain production continuity beyond the North Pit open pit; and • preserve the option of a future BC.

The Board has approved a staged underground development commencing with a standalone SLC. Development of the SLC is common to both pathways and subsequent operation will further de-risk a potential future BC.

Page 5 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Strategic Fit

The underground strategy aims to sustain production at Savage River beyond the North Pit open pit, extend mine life and preserve long-term value for shareholders.

The Board has approved commencement of the SLC as the first stage of the underground development. The initial SLC is required under either long-term pathway: a) Block Cave - the Company’s preferred long-term pathway, which would extend mine life to around 2040, subject to funding and market conditions. Any future BC development remains subject to further studies, funding and a final investment decision. No production target or financial forecast has been prepared for a BC in this announcement; or b) Continued staged SLC mining - the SLC operates on its own to 2035, with further underground options assessed over that period.

The choice between these pathways will be made at a later decision point, informed by SLC operating performance, iron ore market conditions and funding.

The staged SLC plan: • Extends mine life to at least 2035 and maintains continuous ore supply following the completion of the open pit • Delivers a strong NPV under base and downside price scenarios • Is largely self-funded from existing cash reserves and forecast operating cashflow • Reduces near-term capital intensity, with underground capital of approximately A$287 million • Builds underground caving capability and operating data that will reduce the risk of any future Block Cave • Maintains the option to proceed with the Block Cave

The SLC demonstrates a standalone development is feasible in its own right, delivering production to 2035 without further major external investment. This is a step towards the Block Cave, which remains the Company’s preferred long-term development.

Page 6 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Project Assumptions and Financial Outcomes

The financial results set out in Table 2 below are for the approved SLC mining to 2035, and do not include any future Block Cave expansion.

These financial results cover Grange’s Tasmanian operations inclusive of the current open pit mining over 2027-2028. The physicals and financial evaluations are summarised in Table 2 Savage River Underground DevelopmentTable 2.

Table 2 Savage River Underground Development Summary of Key Parameters

Physicals & Financials Units Open Cut + SLC Physicals
Ore Produced Mt 44.1 Ore Grade %DTR 52.3 Total Conc Mt 25.1 Pellet Produced Mt 24.3 Chips Produced Mt 1.21 Price & Revenue
Average Product Price A$/t 181 Average FX A$/US$ 0.68 Total Revenue A$M 4,745 Underground Capital Cost A$M 287 Operating Cost A$M 3,318 Financials

Discount Rate % 8.3 NPV A$M 357 IRR % 43 Payback Years 5.8 EBITDA A$M 616 Cash at Bank¹ A$M 830 Unit Costs

C1 A$/t 132.0 Mining (opencut & underground) A$/t Ore $36 ¹ Cash at bank = closing cash balance per cashflow model at end of Life of Mine Plan (2035).

Page 7 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
The concentrate production profile and cash flow profiles for the SLC case are shown in Figure 1 and Figure 2, below:

Figure 1 Annual production profile for the integrated schedule

Figure 2 Annual cash profile for the integrated SLC schedule

A$‘000

Page 8 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Ore Reserves

The North Pit Underground Ore Reserve was most recently reported in the Company’s annual Mineral Resources and Ore Reserves Statement released on 2 April 2026, with an effective date of 31 December 2025. That statement gives full disclosure of Mineral Resources and Ore Reserves in accordance with the JORC Code. The underground Ore Reserve totals 60.6 Mt at 45.9% DTR (Table 3).

All underground Ore Reserves are classified as Probable. The lower confidence category reflects the mixing of ore and dilution inherent in caving, which reduces certainty in the timing and recovery of ore. The Reserve was estimated using the BC and SLC mine designs in the DFS and remains the basis for the Company’s long-term underground mine plan.

The SLC mines the upper portion of the North Pit orebody, within the footprint of the existing Ore Reserve. All underground ore in the SLC production target comes from material classified as Probable Ore Reserve, and no Inferred Mineral Resources are included. The SLC targets the higher-grade upper portion of the orebody.

Elemental compositions were measured from Davis Tube Concentrate. A cut-off of 15%DTR was used in the calculation of Mineral Resources.

The SLC uses a different mine design and sequence from the BC case. Its production physicals have been updated from previous PGCA flow and recovery modelling. The SLC production target cannot be derived by simple subtraction from the overall Reserve.

The remaining Ore Reserve below and around the SLC remains available to a future BC or alternative underground development. The Ore Reserve will be updated at the next annual Mineral Resources and Ore Reserves Statement, or earlier if a decision is made on the Block Cave.

Page 9 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Table 3 - North Pit Underground Ore Reserve 31 December 2025

Proved Reserves Probable Reserves TOTAL Reserves Tonnes (Mt) 0.0 60.6 60.6 DTR (%) - 45.9 45.9 Fe (%) - 67.6 67.6 Ni (%) - 0.03 0.03 TiO 2 (%) - 0.98 0.98 MgO (%) - 2.07 2.07 P (%) - 0.004 0.004 V (%) - 0.35 0.35 S (%) - 0.03 0.03

• Elemental compositions were measured from Davis Tube Concentrate. • All Underground Ore Reserves are classified as Probable Ore Reserves. No Proved Ore Reserves are reported. • The Ore Reserve includes production from BC and SLC mining estimated using a PGCA flow and recovery model (which accounts for mining dilution and mining recovery), plus ore from underground development with 10% mining dilution. • No grade has been assigned to dilution entering the cave during the mining process or during development. • The production cut-off grade for the BC is ≥ 30% DTR. • The cut-off grade for the SLC is ≥ 28% DTR.

Page 10 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Production Target Statement

The production target of 44.1 Mt comprises 27.8 Mt of underground ore from the SLC and 16.3 Mt of ore from the completion of open pit mining at North Pit and Centre Pit. The underground component is derived entirely (100%) from Probable Ore Reserves.

The open pit component is derived from 15.9 Mt (98%) of Proved Ore Reserves and 0.4 Mt (2%) of Probable Ore Reserves, as reported on 2 April 2026 (effective 31 December 2025), adjusted for subsequent mining depletion, with Centre Pit ore now mined, surveyed and held on stockpile as Proved Ore Reserves. No part of the production target is based on Inferred Mineral Resources, Measured or Indicated Mineral Resources outside Ore Reserves, Exploration Targets or qualifying foreign estimates.

The material assumptions underpinning the production target and forecast financial information are set out in this announcement.

Table 4 - SLC underground production target

Units SLC Ore mined Mt 27.8 Head grade % DTR 57.8 Concentrate Mt 15.4 Production Period Years 2028–2035

Table 5 – Production target by source

Source Open pit (Mt) Underground SLC (Mt) Total Mt % of total Proved Ore Reserves 15.9 0.0 15.9 36% Probable Ore Reserves 0.4 27.8 28.2 64% Measured/Indicated/Inferred Mineral Resources 0.0 0.0 0.0 0.0 Exploration Target 0.0 0.0 0.0 0.0 Total 16.3 27.8 44.1 100%

The estimated Ore Reserves underpinning the production target in this announcement have been prepared by a Competent Person or Persons in accordance with the requirements of the JORC Code (2012 Edition). The Ore Reserves were reported in the Company's announcement titled 'Savage River Mineral Resources and Ore Reserves Update' released to ASX on 2 April 2026 and were prepared by Mr Ben Maynard, a Competent Person who is a Member of The Australasian Institute of Mining and Metallurgy.

Page 11 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
SLC Operation Overview

The SLC operation commences with the recovery of the ore remaining in the northern wall of North Pit. This provides early access to ore and is common development to both pathways.
This allows for progression to the south for the continuation of the SLC as shown below, and contingency production during the establishment and ramp-up of the BC.

Underground Mine Planning

Underground development for the SLC is based on leveraging the existing decline to set up the SLC decline and mining levels.

The SLC design and schedule include:
• Commencing production in the northern wall of the pit, above the pit floor horizon to enable early start-up on multiple levels, reducing the risk of flooding. • The SLC is laid out with transverse crosscuts at 18m spacing and 25m level intervals extending over 10 levels. The northern part of the SLC where the orebody width is below 50m has a longitudinal layout, mining from south to north. • Lowest SLC level is at -275m RL with option to extend the SLC lower or switch to a second lift utilising a block caving method. • Allowances for development and production in areas of challenging ground conditions have been made in the mine schedule, including redrills and crosscut rehabilitation. • Production is designed to supplement surface stockpiles with high grade ore and enable efficient ore blending to fill the concentrate pipeline. • Twin declines to enable one way traffic flow and efficient trucking to support ramping up ore production to 4Mt per year.
• All development in 2027 to be common to the BC-Transition mine plan, allowing option to transition to the BC if required. North Pit SLC initial development North Vent Raise (Exhaust) North Vent Raise (Intake) South Vent Raise (Exhaust) Bulk Water Storage Dams SLC progression Figure 3 - Long Section of NPUG development

Page 12 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Production Profile

Open cut mining continues in North Pit over the next 2 years as the primary ore source. Open cut mining ceases in 2028 allowing underground production to commence and ramp up over the next 3 years. The current production schedule (Figure 4) supplies sufficient ore at the required grade to maintain consistent concentrate production over the next 9 years with options to continue beyond 2035. Further optimisation of the mining schedule will occur during execution to maximise value while maintaining minimal risk to the plant production schedule.

Figure 4 - Planned production integration for transition from Open Pit to Underground

The underground material movement is shown in Figure 5. Production commences in year 3 and ramps up over 2 years. The waste rock is disposed within the existing waste rock dumps or dumped into the open pit.

Figure 5 - Underground material movement showing development and production ramp-up

Page 13 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Capital Cost Estimate

The majority of underground capital costs for the SLC have been built from first principles using supplier and OEM quotes, in-house data, EA agreements and contractor rates and/or industry norms in line with works of a similar nature.

The underground capital costs for the SLC are estimated to be in the order of A$287M, following the methodology used in the DFS. The mining capital cost estimates have been reviewed by an independent reviewer.

Figure 6 - SLC Capital Costs by Major Category

Figure 7 - Annual SLC Capital Costs

Lateral Development Production Capital Vertical Development Ventilation De-Watering UG Services & Facilitites Surface Infrastrucutre & Services Indirect & Contingency

10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000 100,000 2026202720282029203020312032203320342035 A $‘000

Page 14 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Operating Cost Estimate

Underground mining costs have been built up from first principles and in many cases used actual costs, such as labour rates from site activities. An underground benchmarking study of mining productivity and cost estimates for underground mining operations was conducted using the same methodology as the DFS. On the basis of the benchmarking works completed, the development and production unit costs are reasonable and within industry norms.
Infrastructure operating costs have been derived from estimates provided by engineering consultants and from costs at similar mining sites.

C1 costs are total cash operating costs including mining, concentrating, pelletising, and overheads. C1 costs are estimated to be an average of approximately A$132/t concentrate over the life of the mine and average A$126/t of concentrate once the SLC is in full production from 2030.

Figure 8 - Operating Cost by Area for the SLC

Figure 9 - Annual Operating Cost for the SLC

Lateral Development Production Diesel Power Usage Materials Handling Operating Costs Grange Labour Costs Contractor On-Site Costs Project Development & Readiness

50,000 100,000 150,000 200,000 250,000 2026202720282029203020312032203320342035 A $‘000

Page 15 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Project Financial Assessment

The project free cash flows (after tax) were subjected to a discounted cash flow analysis (DCF) using a discount rate of 8.3% (real). The net present value (NPV) of project Free Cash Flow for the SLC case is approximately A$357 million, generating an internal rate of return (IRR) of approximately 43%. The average product price assumed is approximately A$181/tonne.
Current forecast bank balance maintains funds above A$24M through the life of mine and finishes with a balance of A$830M. The current forecast does not include any distributions to shareholders that the Board may elect to make in the future.

Figure 10 - Cash Balance (real) for the SLC

A $ ‘000

Page 16 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Independent Review

The DFS was independently reviewed by AMC Consultants in 2023. The review found no fatal technical or economic flaws and confirmed the work met the standard required for a DFS (ASX release, 28 February 2024). An Independent Technical Expert review, completed in 2026 as part of the project financing process, confirmed the North Pit Underground Project is technically credible. It found no fatal technical, operational or permitting flaws (ASX release, 13 May 2026).

The SLC development option was independently reviewed in August 2026 by Geoff Dunstan of Caveman Consulting. The review covered the SLC mine design, production schedule and mining cost estimates. It found: • The SLC design and schedule are comprehensive and completed to an appropriate level of detail • Planned production rates are reasonable given the location of the levels and the number of crosscuts available • Ring design and development spacings are in line with industry standards
• Mining cost estimates are within expectations, supported by detailed contractor and owner estimates covering workforce, accommodation and equipment.

The review also identified opportunities to lower operating costs by rationalising the mobile fleet. These include fewer longhole drill rigs and truck-loading loaders.

The review did not cover geotechnical conditions or ore recovery modelling. These are addressed by the Company’s geotechnical consultants and are reflected in the mine design and production schedule.

Page 17 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Key Opportunities

There is future opportunity to recover additional material from the lower levels of the SLC by utilising a mass mining method.

Mineralisation also extends at depth which may be accessed by extending the decline. This additional material is not included in the Ore Reserve or the production target and would supplement material delivery. Future mine studies are required to evaluate these opportunities which can be explored further in subsequent stages of project development.

Key Risks

Risk assessments were completed through the DFS and have been updated for the SLC development. During the DFS, the extreme risks were mainly related to inrush and cave management. Controls developed in the DFS have reduced all of them below the extreme rating, and those controls apply equally to the SLC. The current SLC risk register contains no extreme risks. It covers geotechnical, hydrological, mining, workforce, cost, schedule and market risks.

The principal risks for the SLC development, and how they are managed, include: • Inrush and mud rush. Caving below the open pit creates a risk of wet material entering production areas. This is managed through a Cave Management Plan, including an Inrush Hazard Management Plan, draw control, remote monitoring of draw points, and remote-operated equipment. • Ground conditions. Ground conditions in the ore range from fair to very poor, as encountered in the Bulk Sample Drive. Ground support has been designed on that basis, and the mine schedule allows for redrilling and crosscut rehabilitation. • Ore recovery and dilution. Ore recovery is a key driver of project value. It has been estimated using flow and recovery modelling calibrated to the SLC design. • Water inflows. The dewatering system has been designed for flows of up to 1000 L/s, increased from 750 L/s during the DFS.
• Workforce capability. Experienced cave mining personnel are scarce. This will be addressed through recruitment, the use of experienced contractors and, where appropriate, training of existing personnel moving into underground roles and mentoring by specialist consultants. • Ore haulage and supply continuity. Ore will be trucked to surface. As open pit stockpiles are drawn down, plant feed will depend more heavily on underground performance. Haulage capacity is supported by a twin decline with a truck loop. • Market and cost. Financial outcomes are sensitive to iron ore prices, exchange rates and input costs. The SLC has been tested across a range of price scenarios and maintains a positive cash position at prices as low as US$80/t (62% Fe fines).

Work to further reduce these risks will continue during the early execution phase in 2027. It includes updating the Project Execution Plan and the Cave Management Plan for the SLC design.

Page 18 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320
Project Execution

Following Board approval, Grange will proceed to award the underground mining contract and mobilise for SLC development. The first stage of work includes: • Recommencing lateral and vertical development from the existing decline to establish the SLC levels • Completing front-end engineering design, then detailed design for tendering, procurement and construction • Building additional accommodation at Savage River to support the underground mining contractor
• Securing long-lead power infrastructure, including transformers for the site power upgrade

The existing Exploration Decline was designed as the primary access for underground mining and will be leveraged to develop the SLC. Environmental approvals for underground mining are in place. The passage of the mining lease extension legislation, announced on 13 May 2026, gives further certainty over the long-term tenure framework for Savage River.

In parallel with SLC development, the Company will progress BC optimisation and drilling to support studies of a second Block Cave lift, and funding ahead of a potential later decision to proceed to a Block Cave.

Grange will keep the market informed of the progress of the SLC development and its long-term underground strategy.

Table 6 - Key Milestones

Milestone Timing Underground mining contract award & mobilisation Q4 2026 Recommence underground development Q1 2027 Complete front-end engineering design H1 2027 Open pit mining complete 2028 First SLC production ore 2028 SLC ramp-up to approximately 4 Mtpa 2030 Future Life of Mine Plan (BC) decision Subject to funding & market conditions

-ENDS-

This announcement has been authorised by the Board of Directors of the Company.

Page 19 of 19 FACT SHEET Registered Office: 34a Alexander Street, Burnie, Tasmania 7320

Print Date: 24-Sep-26 Page 1 of 15

EPBC 2012/6393 Annual Compliance Report

Reporting Period: 1 July 2025 to 30 June 2026

Print Date: 24-Sep-26 Page 2 of 15

Table of Contents Document control ...................................................................................................................... 2 Key definitions ........................................................................................................................... 3 Purpose ...................................................................................................................................... 4 Background ................................................................................................................................ 4 1 Evidence of compliance .................................................................................................... 5 2 EPBC register extract....................................................................................................... 10

DOCUMENT CONTROL Version Date Description Author Approved 1.0 Sep-26 EPBC Annual Compliance Report 2026 Grange Environment Department Chief Operating Officer

Print Date: 24-Sep-26 Page 3 of 15

KEY DEFINITIONS DCEEW – Department of Climate Change, Energy, the Environment and Water DFTD – Devil Facial Tumour Disease EPBC Act – the Environment Protection and Biodiversity Conservation Act 1999 EPA – Tasmanian Environment Protection Authority Grange Resources - Grange Resources (Tasmania) Pty Ltd MCTD – Main Creek Tailings Dam NRE Tas – Department of Natural Resources and Environment Tasmania
PCE 8808 – is Permit Part B: Permit Conditions - Environmental No. 8808, issued under the Tasmanian Environment Management and Pollution Control Act 1994 dated 24 th March 2014, attached to planning permit DA-69/2013-A, issued under the Tasmanian Land Use Planning and Approvals Act 1993 PCE 10995 - is Permit Part B: Permit Conditions – Environmental No.10995, issued under the Tasmanian Environment Management and Pollution Control Act 1994 dated 5 th April 2022 SDTSF – South Deposit Tailings Storage Facility The Minister – the Federal Environment Minister

EPBC 2012/6393 Annual Compliance Report

Print Date: 24-Sep-26 Page 4 of 15

PURPOSE This report has been compiled to comply with Condition 16 of EPBC approval Savage River
South Deposit Tailings Storage Facility, north-west Tasmania (EPBC 2012/6393). BACKGROUND Grange Resources was issued the EPBC approval 2012/6393 on 24 th of April 2014. The construction of the South Deposit Tailings Storage Facility (SDTSF) commenced during July 2014 under PCE 8808 and EPBC 2012/6393.
The contents of this report should not be used for any other purpose including Rights to
Information requests without the express written permission of Grange Resources. Water chemistry analyses were carried out by NATA accredited Analytical Services Tasmania (AST) laboratories. Online monitoring stations are installed and maintained by Entura. The Reporting Period is 1 st July 2025 – 30 th June 2026.

EPBC 2012/6393 Annual Compliance Report

Print Date: 24-Sep-26 Page 5 of 15

1 EVIDENCE OF COMPLIANCE Condition Compliance Evidence Protection of EPBC Species Condition 1 Grange was approved to clear up to 148 hectares of native vegetation within the vicinity of the action at South Deposit Tailings Storage Facility (SDTSF) under approval EPBC 2012/6393. A total 0.8 ha was cleared in
2025 for the
commissioning of a second tailing deposition point into the SDTSF. See Figure 1 below showing progression of the inundation area.

Figure 1 SDTSF Aerial Image August 2025 Condition 2 Grange continues to provide an induction package for all staff, contractors and visitors at the Savage River Mine site. Records of completion of the induction are stored on Grange’s internal Hub. The induction is compulsory for all staff and
visitors to the Savage River Mine. The induction expires every 24 months and site entry is prohibited without this qualification being current.
The induction is followed up with a toolbox talk that provides detailed
information on the 5 EPBC threatened species and reporting of sightings. This toolbox talk is presented annually at Savage River pre-shift meetings to all staff. The Grange training system automatically notifies staff and contractors when their EPBC threatened species refresher training is due each year. Copies of the training packages are available upon request.

EPBC 2012/6393 Annual Compliance Report

Print Date: 24-Sep-26 Page 6 of 15

Condition Compliance Evidence The main access road into the mine and township have virtual fencing along both sides of the road. These are checked every 12 months to ensure they are in good operating order and batteries were replaced in 2025. Signage remains in place on the mine access road to ensure drivers are aware of the presence of threatened species.
Grange also provides a printed EPBC threatened species protection glovebox
guide for vehicles.
Dayworks team members attend a one-day wildlife training at Trowunna
Wildlife Sanctuary every two years and are due to do refresher training in Q4 2026. The dayworks team are trained in snake handling and healthy captured snakes are relocated and released back into the wild. Condition 3 Immediately prior to commissioning in 2014, North Barker Ecosystem Services completed a preclearance survey, and a subsequent Monitoring Plan was
developed. The Minister approved the Tasmanian devil and spotted-tailed quoll preclearance survey and Monitoring Plan on 16 th June 2014, prior to the
commencement of construction of the SDTSF.
A flora and fauna survey of the SDTSF line 2 was completed in 2026 by an
external contractor, no dens were observed in the survey area. No Tasmanian
devil or spotted-tailed quoll dens have been observed or disturbed during the
reporting period.
Grange is commissioning a Natural Values Assessment in November 2026, which will include the area defined as the vicinity of the action under EPBC 2012/6393. Condition 4 South Deposit Pit Stage 2 mining ceased in March 2017, and it is now a backfill dump pursuant to PCE 10995.
The three water monitoring sites identified in the South Deposit Tailings Storage Facility Water Quality Monitoring and Remediation Plan dated 21 st May 2014 are MCbSD, SD and SRaSR.
MCbSD and SRaSR are sampled monthly. Monitoring of South Deposit ceased in October 2025 with approval to temporarily cease water quality monitoring (ref 20250710-1) by the Tasmanian Environmental Protection Authority (EPA) due to no safe access and the fact the pit water is impounded. South Deposit is currently in closure phase. If any release of water occurs from the South Deposit Pit into the receiving environment water quality monitoring will recommence.

EPBC 2012/6393 Annual Compliance Report

Print Date: 24-Sep-26 Page 7 of 15

Condition Compliance Evidence

Figure 2 South Deposit pit August 2026 The three SDTSF groundwater bores continue to be sampled on a quarterly basis and provide data on groundwater levels. The SDTSF bores groundwater quality is reported in the SDTSF Annual Environmental Review and provided to EPA
under PCE 8808.
Condition 5 All tailings and wastewater associated with the SDTSF complies with Conditions listed under the ‘General’, ‘Effluent’, ‘Monitoring’ and ‘Waste Management’ headings in PCE 8808.
All compliance information and relevant data is provided to the EPA in PCE 8808 Annual Environmental Review submitted by 30 September each year.

Condition 6 Decommissioning and rehabilitation of the SDTSF is managed in accordance with Grange’s Environmental Rehabilitation Plan (ERP). The ERP is updated every
three years and was last updated in October 2023 and submitted to EPA
Tasmania. The ERP is currently in review with an interim draft updated in April 2026. The ERP provides appropriate consideration to the closure and remediation of the SDTSF under three distinct scenarios – sudden closure, temporary cessation, and planned life of mine closure. The ERP satisfies the decommissioning and
rehabilitation conditions under PCE 8808, which in turn satisfies the associated requirements of EPBC approval 2012/6393.
The Savage River ERP closure costings were also externally audited in June 2025.

EPBC 2012/6393 Annual Compliance Report

Print Date: 24-Sep-26 Page 8 of 15

Condition Compliance Evidence Protection of EPBC Species from traffic impacts Condition 7 All existing roadways comply with conditions stipulated in EPBC 2012/6393.
New roads are constructed as per Condition 7 ensuring minimisation of roadkill impacts. All mine roads past the gatehouse are speed limited to 40 km/h.
All roadkill is reported through Grange’s Hub reporting system, and the
dayworks crew remove carcasses the day they occur.
Any roadkill incidents of a threatened species are reported to EPA Tasmania. No devil road deaths occurred in the vicinity of the action, nor the mine site or township, in the reporting period. Monitoring and reporting Condition 8 Grange’s EPBC species register for the vicinity of the action and the wider site is available on the Grange Hub and is updated continuously. The EPBC Annual Compliance Report (this report) is promulgated by 30 September annually at https://www.grangeresources.com.au/announcements and contains a
comprehensive register of all relevant EPBC species in the vicinity of the action.
All sightings of EPBC listed species are reported to Mine Control and the register updated within 24 hours.
The EPBC species sightings register for the reporting period is provided in Section
2 of this report. Condition 9 No request for raw data regarding the Tasmanian devil or DFTD has been
received from any agency by Grange during the reporting period.
The EPBC species register on Grange’s Hub is updated near real time and can
readily be provided to any agency within the 14-day reporting requirement
under EPBC 2012/6393. Condition 10 The approved Tasmanian Devil Monitoring Plan continues to be implemented
with 5 cameras currently in place at locations around the SDTSF, managed by
Granges Environment staff. These cameras are reviewed monthly with all
relevant sightings listed on the EPBC species register. It is encouraging to see the continuation of a healthy population of devils across the site. No Tasmanian devils with DFTD were observed on site during the reporting
period.

EPBC 2012/6393 Annual Compliance Report

Print Date: 24-Sep-26 Page 9 of 15

Condition Compliance Evidence Compensation for unavoidable impacts Condition 11 The required funds were paid to Save the Devil Program via NRE Tas in 2015 & 2016 by the required timeframe. No further payment is outstanding.
Condition 12 No deaths occurred within the vicinity of the action during the reporting period. Condition 13 The Department was advised of the commencement of the project on the 10 th

of July 2014. Condition 14 Grange has complied with all conditions under EPBC 2012/6393 during the reporting period. Condition 15 Grange maintains all required records relevant to the conditions of approval and is subject to audit by DCEEW or EPA at any time.
Condition 16 This Annual Compliance Report has been prepared to satisfy Condition 16. Condition 16a An extract from the EPBC register is provided in Section 2. Condition 16b Grange has previously provided receipt of the total payment; no further
payment is outstanding.
Condition 16c This Annual Compliance Report has been prepared to satisfy Condition 16c. Condition 16d There have been no incidences of non-compliance against the conditions of
EPBC approval 2012/6393 during the reporting period. Condition 17 No request has been received during the reporting period. Condition 18 There have been no other changes to the approved activity during the reporting period not otherwise stated in this report.
Condition 19 No request has been received during the reporting period. Condition 20 Not applicable.
Condition 21 All required documents for the reporting period are available on the Grange
Resources public website, namely the EPBC species r egister, and the EPBC
Annual Compliance Report (this report).

EPBC 2012/6393 Annual Compliance Report

Print Date: 24-Sep-26 Page 10 of 15

2 EPBC REGISTER EXTRACT Extract of Grange’s EPBC animal sighting register, filtered to sightings within the vicinity of the action under EPBC 2012/6393, established under Condition 8, for the reporting period is shown below.
EPBC species sightings shown are for the reporting period of 1 July 2025 to 30 June 2026 in the vicinity of the action: • Tasmanian Devil sightings: 60 • Tasmanian Wedge-tailed Eagle sightings: 0 • Spotted-tail Quoll: 1

EPBC 2012/6393 Annual Compliance Report

Print Date: 24-Sep-26 Page 11 of 15

EPBC 2012/6393 Annual Compliance Report

Print Date: 24-Sep-26 Page 12 of 15

EPBC 2012/6393 Annual Compliance Report

Print Date: 24-Sep-26 Page 13 of 15

EPBC 2012/6393 Annual Compliance Report

Print Date: 24-Sep-26 Page 14 of 15

EPBC 2012/6393 Annual Compliance Report

Print Date: 24-Sep-26 Page 15 of 15

End Report

Prompts

Grange Resources Limited (ticker GRR), listed in Australia.

ETFs Holding Grange Resources Limited

ETF Weight in ETF Shares Market value As of
AVDE 0.00% 240,025 $ 16.181K Nov 16, 2026
AVDV 0.00% 4,529,711 $ 305.368K Nov 16, 2026
AVDS 0.00% 39,763 $ 2,680.60 Nov 16, 2026