September 2026 Quarterly Report
New contractor ramping up and consistent
grades set Bellevue up for growth in FY27
Hedge book continues to be reduced ahead of schedule and is set to be eliminated
in FY27, paving way for significant growth in free cash flow
Production
• September 2026 quarterly gold production was 35,585 ounces (June 2026 quarter: 41,643
ounces). Gold sold totalled 35,979 ounces at an average realised price of A$4,980 per ounce
(including voluntary early delivery of 11,150 ounces into forward sales contracts) and a project all-
in sustaining cost of A$3,096 per ounce (June 2026 quarter: A$2,604 per ounce).
• As announced previously
1
, the mining contractor changeover was completed as planned in August
2026, although the ramp-up by the new contractor was slower than expected. The impacts of the
slower contractor ramp-up are expected to be confined largely to the September 2026 quarter,
with the deferred production to be recovered in subsequent quarters.
• FY27 production guidance is unchanged at 150,000-170,000 ounces and FY27 project all-in
sustaining cost remains guided at between A$2,800 and A$3,100 per ounce.
• Ore mined during the quarter totalled 203,013 tonnes at 4.7 grams per tonne of gold for 30,763
ounces. Mined grades remained consistent quarter on quarter as mining is now well established
in key mining areas.
• Ore processed during the quarter totalled 250,702 tonnes at 4.6 grams per tonne of gold. Gold
production was supplemented by surface stockpiles.
Finance & Corporate
• Underlying free cash flow, before voluntary future hedge book pre-deliveries, of $48 million
2
(June
2026 quarter: $110 million), was lower than the prior quarter due to lower gold sales and higher
total cash expenditure, largely as a result of guided capital expenditure associated with the mining
contractor transition and paste plant construction.
• Forward gold sales commitments have been reduced by a further 11.2koz to 57.5koz (30 June
2026: 68.7koz), through voluntary pre-delivery against contracts with maturities in the June 2027
and September 2027 quarters.
• Bellevue continues to target full extinguishment of the hedge book in FY27.
• Following the pre-delivery of gold into forward sales contracts, cash and gold on hand on 30
September 2026 increased to $213 million (June 2026 quarter: $206 million).
1
Refer the Company’s ASX announcement dated 21 September 2026 titled ‘Exploration Update and Annual Resource & Reserve Statement'.
2
Underlying free cash flow = sum of operating and investing cash flows (including the effects of any contracted current quarter hedge book
deliveries), plus or minus the movement in bullion awaiting settlement, gold dore and bullion value (at traded price or closing quarter end gold
price as appropriate) before any non-mandatory debt repayments or future quarter hedge book deliveries. Deliveries into forward contracts
involve receiving the relevant contract price (as adjusted for actual delivery date versus contract maturity) and estimates of FCF before pre-
deliveries have, consequently, been estimated using the realised spot price for the quarter.
ASX Announcement
20 October 2026
P a g e | 2
Exploration
• Infill drilling at Deacon North has defined new high-grade plunging shoots of mineralisation that
have been incorporated into mine planning. Recent Deacon North results include
1
:
o 9.3m @ 62.1g/t gold o 8.9m @ 31.0g/t gold
o 4.6m @ 50.3g/t gold o 5.2m @ 32.1g/t gold
o 6.7m @ 23.5g/t gold o 5.1m @ 27.4g/t gold
o 6.4m @ 20.0g/t gold o 5.3m @ 21.9g/t gold
• Drilling and a downhole electromagnetic survey at Westralia have identified a number of
promising anomalies.
• Development of the Southern Belle Decline has established new underground drill platforms that
will allow drilling in FY27 to step further south into Tribune South and towards the Southern Belle
Position under Lake Miranda.
Sustainability
• The Bellevue Gold Project, the world’s first net zero (Scope 1 and Scope 2) emissions gold mine,
was honoured to be chosen to supply the gold for the regilding of St Paul’s Cathedral in London
3
.
Bellevue Managing Director and Chief Executive Officer, Darren Stralow said: “We made good progress
during the quarter towards our key operational and financial objectives for FY27.
“Our new contractor is ramping up, with further gains expected in the December quarter as it relocates
workers from a completing project to Bellevue.
“Grades were consistent and in line with our model, reflecting the fact that the mine is now well-advanced
and has five long-term mining areas.
“At the same time, we continued to reduce the hedge book, ensuring we are well on track to eliminate it
altogether during the course of FY27.
“This will set us up for strong growth in free cash flow as we gain full exposure to the spot price”.
3
Refer to the Company's ASX announcement dated 30 September 2026 titled 'Bellevue to supply gold for regilding of St Paul’s Cathedral'.
ASX Announcement
20 October 2026
P a g e | 3
Overview
Bellevue Gold Limited (Bellevue or Company) (ASX: BGL) is pleased to present its Quarterly Activities
Report for the September 2026 quarter (Quarter), for operations at its 100% owned Bellevue Gold Project
(Project or Mine) located in the Goldfields of Western Australia.
The Company recorded no Lost Time Injuries (LTI) during the Quarter, resulting in the 12-month rolling
Lost Time Injury Frequency Rate (LTIFR) reducing to 2.0.
Gold produced for the Quarter was 35.6koz (June 2026 quarter: 41.6koz). Gold sales were 36.0koz (June
2026 quarter: 40.7koz) and were sold at an average realised gold price, inclusive of hedge book pre-
deliveries, of A$4,980 per ounce (oz) and produced at an all-in sustaining cost (AISC) of A$3,096/oz (June
2026 quarter: A$2,604/oz).
Mined grades and processed grades remained consistent quarter on quarter as ore continues to be
sourced from five core long term mining areas. Mine development and mined tonnes reduced quarter on
quarter as progress was impacted by the ramp-up of the new mining contractor at site.
Metallurgical recovery averaged 94.9% for the Quarter. Surface stockpiles are estimated at 10kt at the end
of the Quarter (June 2026 quarter: 47kt) with stocks being depleted during the Quarter to supplement the
lower delivery of ore from the mine.
The AISC per ounce for the Quarter remained within guidance despite the lower production for the
Quarter. Going forward, AISC now includes the reallocation of development capital at Deacon North to
sustaining capital from non-sustaining capital following establishment of this fifth mining area.
Growth capital was higher quarter on quarter as guided, following capital expenditure on construction of
the paste plant and one-off costs on underground plant and equipment associated with the changeover
of mining contractor.
FY27 production guidance is unchanged at 150,000-170,000oz and Project AISC remains guided at between
A$2,800/oz and A$3,100/oz. AISC and non-sustaining capital costs are both guided to decrease in the
second half of the year with the mining contractor transition complete and with remaining paste plant and
other ancillary capital expenditure to support growing operations being substantially incurred in H1 FY27.
Non-sustaining capital remains unchanged at $90-100 million and exploration expenditure is guided at
$25-30 million.
ASX Announcement
20 October 2026
P a g e | 4
Table 1: Production & Cost Summary.
Units
Sept 2026
Qtr
June 2026
Qtr
Mar 2026
Qtr
Dec 2025
Qtr
FY27
YTD
Total Development Advance m 2,646 4,110 3,403 4,161 2,646
Development ore tonnes t 80,017 127,847 83,742 97,653 80,017
Development ore grade g/t 3.2 5.0 5.5 2.6 3.2
Stoping ore tonnes t 122,996 187,453 209,057 209,115 122,996
Stoping ore grade g/t 5.7 4.3 4.3 4.3 5.7
Total mined ore tonnes t 203,013 315,300 292,799 306,768 203,013
Total mined ore grade g/t 4.7 4.6 4.6 3.8 4.7
Processed ore tonnes t 250,702 298,772 282,927 280,671 250,702
Processed grade g/t 4.6 4.5 4.7 3.7 4.6
Recovery % 94.9% 96.0% 94.6% 96.1% 94.9%
Gold produced Oz 35,585 41,643 40,745 32,031 35,585
Gold poured Oz 35,142 41,669 39,737 31,656 35,142
Gold sold Oz 35,979 40,671 39,754 31,905 35,979
Realised Gold Price
4
A$/Oz 4,980 4,180 3,459 4,292 4,980
Gold Revenue $M 179.2 170.0 137.5 136.9 179.2
Mining $M 38.1 51.4 42.1 43.1 38.1
Processing $M 23.8 22.2 23.7 21.8 23.8
Site Services $M 8.0 7.2 6.8 5.8 8.0
Royalties $M 11.1 12.6 14.1 10.5 11.1
Inventory Movement $M 4.5 (3.4) (0.9) (2.7) 4.5
Cash Cost $M 85.5 90.0 85.8 78.5 85.5
Sustaining Capital
5
$M 25.9 15.9 16.7 16.9 25.9
Project All-In Sustaining Cost $M 111.4 105.9 102.5 95.4 111.4
Project All-In Sustaining Cost A$/Oz 3,096 2,604 2,578 2,989 3,096
Exploration
6
$M 2.5 5.4 3.3 3.7 2.5
Growth/Non-Sustaining Capital
5
$M 39.2 36.3 21.9 17.5 39.2
Total Project Costs $M 153.1 147.6 127.7 116.6 153.1
Corporate Cost $M 5.8 5.4 6.0 5.8 5.8
Depreciation & Amortisation
7
$M 54.6 57.9 56.6 47.7 54.6
Net Mine Cash Flow
8
$M 31 19 9 18 31
Free Cash Flow (after any hedge book
pre-deliveries)
$M 9 28 18 11 9
4
Realised gold price & revenue inclusive of gold sales at spot & forward contract prices. AISC/oz calculated on a per ounce of gold sold basis.
5
From the start of FY27 Deacon North has been considered in commercial production, resulting in a higher proportion of capital costs
associated with mine development being classified as sustaining capital and included in AISC rather than all being in non-sustaining capital as in
FY26. From the start of FY27 lease costs are included in sustaining and non-sustaining capital, with amounts apportioned based on activity cost
drivers. A total of $5.5m is included in sustaining capital and $1m in non-sustaining capital.
6
Includes an allocation of in mine development costs to access and establish drill platform locations and regional exploration.
7
Amount includes D&A incorporated in inventory movements for statutory reporting purposes and excludes D&A included in corporate and
admin costs ($0.1m YTD).
8
Net Mine Cash Flow = Revenue (from spot & forward sales), less Cash Costs (excluding inventory movements), Sustaining Capital, Exploration
and Growth Capital.
ASX Announcement
20 October 2026
P a g e | 5
Operations
Underground Mining
Total underground movement for the Quarter was 203,013 ore tonnes at 4.7g/t gold consisting of 80,017t
at 3.2g/t gold of development ore and 122,996t at 5.7g/t gold of stoped ore. The Quarter saw continued
mining from higher-grade stoping areas at Tribune, Deacon and Viago and the grade mined was largely
unchanged quarter on quarter as a result.
Total development advance for the Quarter was 2,646 metres from five jumbos. Mining and development
were expected to drop off during the quarter due to the contractor transition, however, as previously
announced,
1
the speed of the ramp-up was slower than expected.
Mining Contractor Transition
The transition from Develop Global Limited (Develop) (ASX: DVP) to Barminco Limited (Barminco) (a
subsidiary of Perenti Limited (ASX: PRN)) as underground mining contractor was completed on 1 August
2026. During July 2026, Develop progressively demobilised its workforce and equipment in preparation for
the handover.
Since taking operational control, Barminco has progressively ramped up mining activities. The ramp-up has
been slower than anticipated due to a combination of workforce availability, equipment commissioning
requirements and restricted access to certain planned high-grade stoping areas. The impacts of the slower
contractor ramp-up are expected to be largely confined to the September 2026 quarter, with the deferred
production expected to be recovered in subsequent quarters.
Workforce availability is expected to improve during the December 2026 quarter as Barminco completes
another Western Australia mining project and labour transfers to the Bellevue Gold Project.
FY27 production and cost guidance remains unchanged. As previously guided, production is expected to
benefit progressively from all five mining areas being fully established during FY27, together with an
increasing contribution from the high-grade Deacon North mining area in the second half.
Deacon North high-grade shoots
The broader Deacon area contains multiple high-grade plunging shoots across Deacon Main and Deacon
North. The scale and geometry of recently defined shoots at Deacon North are comparable to those
defined and mined within the Deacon Main mining area. Infill drilling during H2 FY26 at Deacon North
confirms the continuity of high-grade mineralisation within the infilled area shown in Figure 1. The new
drilling is showing semi-massive pyrrhotite shoots and high-grade drill results of similar style to the Deacon
Main shoots. Deacon North is an important contributor to the FY27 mine schedule. Results reported during
the Quarter include
1
:
o 9.3m @ 62.1g/t gold o 8.9m @ 31.0g/t gold
o 4.6m @ 50.3g/t gold o 5.2m @ 32.1g/t gold
o 6.7m @ 23.5g/t gold o 5.1m @ 27.4g/t gold
o 6.4m @ 20.0g/t gold o 5.3m @ 21.9g/t gold
ASX Announcement
20 October 2026
P a g e | 6
Figure 1: Deacon North high-grade infill results.
9
Processing
The processing plant achieved lower throughput rates quarter on quarter of 250,702t processed at 4.6g/t
gold and 94.9% recovery for 35.6koz. Production was impacted by lower ore delivery from the
underground mine. This ore was supplemented by processing surface stockpiles during the Quarter.
Metallurgical recovery was slightly lower quarter on quarter and was impacted by the inconsistent delivery
of ore feed. Metallurgical recoveries are expected to return to the longer-term average as the rate of
mining ramps up through the first half of FY27.
At the end of the Quarter, contained metal in ROM and crushed stocks decreased compared to the prior
quarter, and totalled 10kt at 4.24g/t gold for 1.4koz. Stockpiles were progressively depleted during July
2026 and August 2026 but were rebuilding during the month of September 2026.
Paste Plant
Construction of the paste plant continues on schedule. The 2,000m
3
tailings holding tank is now in place
(Figure 2). Commissioning remains on schedule for mid FY27, with paste filling to commence immediately
thereafter.
9
For previously reported drilling results from Deacon North refer to the Company's ASX announcements dated 21 September 2026, 19 May
2026, 27 November 2025, 5 August 2019, 17 December 2019, 24 February 2020, 27 May 2020, 1 October 2020, 18 February 2021, 16 March
2021, 15 April 2021, 23 June 2021, 21 September 2021, 15 February 2022, 5 April 2022, 4 May 2022, 25 July 2024 and 21 September 2026.
ASX Announcement
20 October 2026
P a g e | 7
Figure 2: Paste Plant construction – October 2026.
Finance & Corporate
Finance
Cash and gold on hand increased to $213.2 million at the end of the Quarter. Underlying free cash flow
before making voluntary hedge contract pre-deliveries was $47.6 million, after incurring $41.7 million on
non-sustaining and exploration capital. Approximately $39 million was directed to pre-delivery of hedge
book obligations, resulting in free cash flow after pre-deliveries of $8.9 million.
Non-sustaining capital is expected to progressively reduce over the next few quarters, as the Quarter
included the one-off purchase of underground infrastructure equipment from the outgoing contractor and
also saw the highest expected quarterly expenditure related to paste plant construction. Exploration
expenditure is expected to increase in subsequent quarters, as drill rigs are increasingly directed to reserve
and resource growth.
Underlying free cash flow was lower than the prior quarter due to lower gold sales, higher total cash
expenditure, largely as a result of guided capital expenditure associated with the mining contractor
transition and paste plant construction, and net cash outflows from working capital movements. Following
the voluntary hedge contract pre-deliveries, free cash flow of $8.9 million was generated in the Quarter.
The waterfall chart below (Figure 3) provides a reconciliation for the Quarter.
In past periods, the lease costs associated with the hybrid renewable power station were absorbed across
cash, sustaining and non-sustaining costs using operational activity drivers. As previously reported, the
FY27 guidance and, accordingly, September 2026 results, incorporate all such lease costs as either
sustaining or non-sustaining capital, with none included in cash costs. While the effects of these costs
included in cash costs have previously been disclosed by way of footnote to quarterly reports to allow
reconciliation against the cost of goods sold in statutory earnings reporting, these amounts have now been
ASX Announcement
20 October 2026
P a g e | 8
included solely in sustaining and non-sustaining capital to facilitate simpler reconciliation between
quarterly reporting and statutory earnings going forward.
Figure 3: September 2026 quarter liquidity waterfall (A$ millions).
10
As at 30 September 2026, Bellevue had the following cash, bank debt and gold balances.
Table 2: Cash, debt & bullion balances as at 30 September 2026.
Units 30 Sep 26 30 Jun 26 31 Mar 26 31 Dec 25
a) Cash & Cash Equivalents A$M 188.5 195.4 167.7 165.1
b) Restricted Cash A$M - - - -
c) Bullion awaiting settlement
11
A$M 24.3 8.6 13.0 -
d) Gold on hand A$M 0.4 2.4 - -
e) Total Liquidity (a + b + c + d) A$M 213.2 206.4 180.7 165.1
f) Bank Debt A$M (100.0) (100.0) (100.0) (100.0)
g) Net Cash/(Debt) (e + f) A$M 113.2 106.4 80.7 65.1
Hedging
Underlying free cash generation facilitated further reducing hedge book commitments through pre-
deliveries during the Quarter. Forward gold sales commitments have been reduced by a further 11,150oz
through voluntary pre-delivery against hedge commitments in the June 2027 and September 2027
quarters (Table 3). Bellevue is now free of mandatory hedge book deliveries until the end of September
2027. Bellevue continues to target full extinguishment of the hedge book during FY27.
10
Statutory gold sales revenue was $179.2 million for the quarter with a reduction in gold on hand of $2.0 million. That is, noting that the
waterfall chart includes notional indicative gold sales values as if gold had been sold at spot (average of realised spot price during the quarter of
A$6,054/oz) for the quarter, rather than voluntarily delivering into future hedge commitments early. Pre-deliveries entail the physical delivery of
gold produced against forward sale commitments early in return for the applicable forward price for early delivery.
11
Bullion awaiting settlement is gold sold before the end of the Quarter and awaiting receipt of proceeds, generally within two business days.
ASX Announcement
20 October 2026
P a g e | 9
Table 3: Gold forward sales commitments as at 30 September 2026.
Quarterly Gold Sales Hedged (Oz) Gold Price (A$/oz)
30-Sep-27 19,000 2,927
31-Dec-27 20,625 2,909
31-Mar-28 17,875 3,380
Total / Average Price 57,500 3,061
Exploration & Growth
The Bellevue Gold Project is increasingly displaying the characteristics of a broader mining camp. Mining
camps are common across the Eastern Goldfields of Western Australia and are typically defined by multiple
orebodies mined progressively over extended operating lives.
The FY27 exploration budget of $25-30 million will support this push to expand Resources and Reserves.
Westralia Drilling
Surface drilling within the Westralia Area is at an early exploration stage and is focused on identifying new
mineralised structures below the historic Westralia underground workings and near the current Marceline
mining area.
Drilling has previously intersected mineralisation including 3.44m at 18.45g/t gold located approximately
140m east of existing underground development at Marceline
12
.
A downhole electromagnetic (DHEM) survey program has been completed to support Bellevue’s ongoing
exploration targeting, leveraging a geophysical technique that has previously assisted in identifying
sulphide-associated gold mineralisation. The work has identified several new structures (Figure 4),
including a target below the historic Westralia workings that aligns well with the mineralised structure and
coincides with a strong DHEM anomaly.
Surface drilling is currently focused on drill testing to the west and down dip of the Bellevue mineralisation.
Drilling and DHEM interpretation is ongoing at Westralia, and Westralia will continue to be drill tested
from surface and underground in FY27.
12
Refer to the Company's ASX announcement dated 29 April 2026 and titled 'Quarterly Activities Report'.
ASX Announcement
20 October 2026
P a g e | 10
Figure 4: Bellevue schematic cross section showing 2026 surface drilling & recent DHEM plates at Westralia.
Tribune South
As previously reported
13
, development of the Southern Belle Decline has established new underground
drill platforms, allowing drilling to step south into Tribune South towards the Southern Belle Position.
Drilling completed to date has intersected encouraging results including 3.5m at 44.96g/t gold (previously
reported). Drilling is expected to continue advancing south as additional platforms become available.
FY27 Mineral Resource and Ore Reserve Statement
An updated indicated and inferred Mineral Resource
for the Bellevue Gold Project of 9.8Mt at 8.6g/t gold
for 2.7Moz gold was reported during the Quarter and is current as at 1 March 2026.
14
The updated Mineral
Resource incorporates 193,000m of underground diamond drilling completed since the previous resource.
Total Project Ore Reserves have been updated to 6.8Mt at 4.5g/t gold for 1.0Moz gold.
1
The updated Probable
Ore Reserve is based on the updated Mineral Resource together with mining depletion incurred since the
previous Ore Reserve statement (1 March 2025 - 1 March 2026).
13
Refer to the Company's ASX announcement dated 16 June 2026 and titled 'Operations on track & drilling commenced at Tribune South'.
14
2.7Moz global Resource consists of 5.5Mt at 9.3g/t gold for 1.6Moz gold Indicated and 4.3Mt at 7.8g/t gold for 1.1Moz gold Inferred. Refer
the Company’s ASX announcement dated 21 September 2026 titled ‘Exploration Update and Annual Resource & Reserve Statement'.
ASX Announcement
20 October 2026
P a g e | 11
Sustainability
Bellevue continues to achieve high renewable energy usage at the Project. The power station performed
well in the Quarter, albeit with lower renewable energy rates during winter as expected, with renewable
energy averaging 75.2% for the Quarter.
During the Quarter, Bellevue was selected to supply the gold for the regilding of St Paul’s Cathedral in
London. Bellevue will sell the gold, which will adorn the top of the London landmark, where it will be used
to gild the ball and cross (atop the dome) and the Golden Gallery.
Bellevue was chosen primarily because of its sustainability and traceability features. Bellevue continues to
work closely in partnership with ABC Refinery and Single Mine Origin (SMO), in order to expand the
network of customers who value a differentiated gold product with known provenance surrounding its
original extraction.
During the Quarter, Bellevue Gold published its 2026 Sustainability Report. Subsequent to the end of the
Quarter, Bellevue was awarded the prestigious Golden Gecko Award for Environmental Excellence by the
WA Department of Mines, Petroleum and Exploration. The Golden Gecko Award recognises and rewards
leading practices, innovation and excellence in environmental management in the resource sector of